Question 16/22

A large company of more than 400 people changes from the Waterfall to the Agile framework. The company uses the approach of applying Scrum to all projects in the organization using an all-in scenario.
The leaders are reluctant to fully commit to Scrum and there are no experienced Scrum Masters available within the organization yet. Six months later, Scrum has failed in the company. Many different applications of Scrum have been tried with varying degrees of success. The company gives up and returns to the Waterfall approach.
What is the most likely reason that the transition did not work?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (22q)
1 commentQuestion 1: Inexperienced Agile teams tend to overestimate how much they...
1 commentQuestion 2: A Development Team consists of various different roles: anal...
Question 3: Which Scrum meeting helps an organization become engaged in ...
Question 4: For a cross-functional team, it is important that all skills...
Question 5: What is the recommended way of removing the resistance prese...
Question 6: A Scrum Master is teaching Agile estimation techniques using...
Question 7: A Scrum Team has agreed on the following definition of Poten...
Question 8: A company is already using Scrum very successfully within th...
Question 9: The Product Owner informs the team that the release will be ...
Question 10: What is one of the risks if the Scrum Master is also a progr...
Question 11: Your company wants to be highly responsive to bug reports or...
2 commentQuestion 12: What is the difference between NPV and IRR? A: NPV is a meas...
Question 13: During a Sprint Planning, a team has picked three User Stori...
Question 14: When two companies merge, there is often a lack of communica...
Question 15: The ability for a Scrum Team to self-organize around the goa...
Question 16: A large company of more than 400 people changes from the Wat...
Question 17: The Scrum-of-Scrums meeting is designed to allow clusters of...
Question 18: A company changes to Scrum. This gets some people out of the...
Question 19: As items are developed and removed from the top of the Produ...
Question 20: What is the main reason to limit Scrum Teams to 9 team membe...
1 commentQuestion 21: You realize that the most experienced member on your team, w...
Question 22: A team finds bugs in a feature. What is the best action to t...