Valid PK0-005 Dumps shared by EduDump.com for Helping Passing PK0-005 Exam! EduDump.com now offer the newest PK0-005 exam dumps, the EduDump.com PK0-005 exam questions have been updated and answers have been corrected get the newest EduDump.com PK0-005 dumps with Test Engine here:
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Correct Answer: C
Milestones are activities with zero duration that are added to a project schedule by a project manager. Milestones are significant events or achievements in a project that mark the completion of a phase, deliverable, or task. Milestones can help to track and measure the progress and performance of a project and communicate it to stakeholders.