The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (62q)
Question 1: A third party needs to perform a short-term task for which t...
Question 2: A project manager receives an escalation from an external gr...
Question 3: A project manager was not part of a contract negotiation. Th...
Question 4: During a code implementation, a senior developer and junior ...
Question 5: During a quality analysis review, the causes of several issu...
Question 6: Due to budgetary and time constraints, a PM scheduled a meet...
Question 7: A project manager reports that the implementation of a new s...
Question 8: A project manager has decided to wait until all requirements...
Question 9: Halfway through a project, the sponsor states that the proje...
Question 10: An institution wants to implement software solutions to help...
Question 11: A project coordinator has started a new project and is revie...
Question 12: When creating a project schedule, a project manager adds act...
Question 13: Which of the following is a quality assurance tool?...
Question 14: During a brainstorming session, a project team is elaboratin...
Question 15: A PM has identified all the resources involved in a project....
Question 16: Which of the following tools is best to use for storing less...
Question 17: A PM wants to add a chart to the monthly status report to sh...
Question 18: A project manager is coordinating multiple teams of six peop...
Question 19: Two developers are discussing the design solution for a part...
Question 20: Due to multiple changes, the sign-off for the project scope ...
Question 21: A project manager is assigned to a multinational project wit...
Question 22: A project sponsor is struggling to provide the latest projec...
Question 23: A PM is working on the preliminary scope statement and ident...
Question 24: Which of the following BEST illustrates how team members wit...
Question 25: A project manager buys an extended warranty for a set of ser...
Question 26: A project team is defining operational training, discussing ...
Question 27: A visual that displays team progress was created for stand-u...
Question 28: An IT intern was assigned to set up workstations as part of ...
Question 29: Which of the following is a test that is done on an existing...
Question 30: During a brainstorming meeting, a project manager identifies...
Question 31: Which of the following activities would be performed during ...
Question 32: A piece of equipment has malfunctioned and is stalling the c...
Question 33: A risk management team for a software project decided to out...
Question 34: During a gate review meeting, the deliverable was rejected b...
Question 35: Because the project team lacks hands-on experience, the proj...
Question 36: An opportunity emerged in the middle of a project life cycle...
Question 37: The project team determines that software installation can o...
Question 38: Which of the following BEST describes how an organization sh...
Question 39: Which of the following would be the NEXT document a project ...
Question 40: A hurricane delays the shipment of critical equipment for a ...
Question 41: A PM received feedback from the project sponsor that the res...
Question 42: A company that is implementing an updated version of its mai...
Question 43: Given the following velocity chart: (Exhibit) Which of the f...
Question 44: Someone claiming to be from a tax agency sent an email to a ...
Question 45: A PM is working on a strategy to store records. Which of the...
Question 46: As part of the planning phase, a PM has defined tasks, durat...
Question 47: A project is running over budget, and due to new legislation...
Question 48: Refer to exhibit. (Exhibit) Given the following network diag...
Question 49: A project team evaluated the performance of a new reporting ...
Question 50: Which of the following should be the PRIMARY basis for estab...
Question 51: A project manager identifies stakeholders who will be impact...
Question 52: A project manager has been very diligent in maintaining the ...
Question 53: Which of the following activities would a project manager pe...
Question 54: During a status meeting, the development team reviews work a...
Question 55: Which of the following offers administrators more direct con...
Question 56: While managing a project, a PM is assigned to work on a seco...
Question 57: A project implementation partner and the project manager dis...
Question 58: Which of the following statements best describes a content m...
Question 59: During the execution phase of a project, the project team fa...
Question 60: Which of the following is a reason to use a SOW on a project...
Question 61: A stakeholder works in a remote location and has not been re...
Question 62: A project manager was just assigned to a new project. Which ...