Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 122/190

During the execution phase, the project manager discovered that the testing phase is dependent on completion of the vendor's tasks. The project team has just informed the project manager their activities are almost complete, and they would like permission to begin testing. The vendor is not scheduled to deliver the products for two months.
Which of the following should have occurred to prevent this issue?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (190q)
Question 1: A project manager was directed to complete a project sooner ...
Question 2: A department manager asks a project manager about the status...
Question 3: Two team members completely disagree on how to complete a sp...
Question 4: A project has fallen behind schedule. Upon investigation, th...
Question 5: Which of the following are the components of a RACI matrix?...
Question 6: An external customer has requested a modification of the pro...
Question 7: The Chief Executive Officer (CEO) has announced that the har...
Question 8: During a project, the project manager discovers there is ins...
Question 9: A project team is identifying, rating the probability of, an...
Question 10: A project sponsor and Chief Information Officer (CIO) disagr...
Question 11: A vendor has accepted a proposed project from a customer. Wh...
Question 12: A project has activities on the critical path that must be c...
Question 13: The project schedule performance index is 1.1, and the cost ...
Question 14: A project manager who is part of a global team wants to have...
Question 15: A project team is composed of numerous team members who are ...
Question 16: A project team is comprised of a mix of in-house and virtual...
Question 17: The supervisor asks an engineer to be a project manager with...
Question 18: A project manager is successfully adhering to an eight-week ...
Question 19: A company has dictated project scope changes but has stated ...
Question 20: A project manager is successfully adhering to an eight-week ...
Question 21: There are four parallel paths on a network diagram. The summ...
Question 22: Given the following sprint: (Exhibit) Which of the following...
Question 23: A PM receives notification that an issue will impact a deliv...
Question 24: A project manager wants to introduce the practice of a WBS t...
Question 25: A project manager is determining a project's critical path t...
Question 26: While developing a project schedule, the project manager is ...
Question 27: A project has a BAC of $850,000. The project manager has ide...
Question 28: Which of the following risk strategies is represented by the...
Question 29: The chairperson of the board is visiting from another countr...
Question 30: An authorized change to a construction project was implement...
Question 31: A project manager is creating the monthly report for top man...
Question 32: Which of the following documents should be used FIRST when a...
Question 33: The PMO is responsible for: (Choose two.)...
Question 34: A project manager is mapping qualifications and available pe...
Question 35: A new project charter is being drafted. Which of the followi...
Question 36: An American publisher is participating in a workshop in Hong...
Question 37: New requirements were introduced during the execution phase ...
Question 38: Which of the following describes a burn rate?...
Question 39: A project requires daily status updates. Which of the follow...
Question 40: Which of the following activities are associated with the cl...
Question 41: According to the communication management plan, the project ...
Question 42: Tasks B and D start after Task A is completed. Task C starts...
Question 43: Two team members have concluded that documentation is not re...
Question 44: In which of the following organizational structures would a ...
Question 45: The project sponsor wishes to implement a 24/7 solution for ...
Question 46: An active project has a CPI of 0.92. Which of the following ...
Question 47: A non-stakeholder approaches the project manager and asks if...
Question 48: Which of the following is a characteristics of a matrix orga...
Question 49: An outsourced project team member approaches the project man...
Question 50: In a project with a BAC of $235,000, the CPI is 0.80, and th...
Question 51: A project manager is providing the lessons learned for a pro...
Question 52: A project manger received a change request, immediately docu...
Question 53: Which of the following is a characteristics of a matrix orga...
Question 54: A company hires an outside vendor to provide 24/7 support. W...
Question 55: During an ad-hoc meeting, the PM notifies the sponsor that w...
Question 56: A local company is part of a hostile takeover by a multinati...
Question 57: Two team members have concluded that documentation is not re...
Question 58: An active project is focused on quality assurance of the del...
Question 59: A risk with a high probability and medium consequence to a p...
Question 60: Project A is delivering the foundation for Project B. Constr...
Question 61: Which of the following measurements would give the project m...
Question 62: A project manager is creating the monthly report for top man...
Question 63: A project manager received a change request, immediately doc...
Question 64: The project schedule performance index is 1.1, and the cost ...
Question 65: Which of the following describes how a project is related to...
Question 66: After identifying all known tasks, the project manager has s...
Question 67: Which of the following is used to perform a root cause analy...
Question 68: A manager is reviewing some projects with two project manage...
Question 69: A project team is mainly based in a metropolitan area. The t...
Question 70: Which of the following are examples of organizational change...
Question 71: A project team is comprised of a mix of in-house and virtual...
Question 72: During a meeting, the project manager abruptly interrupts th...
Question 73: If a project sponsor wants to know the current status and pr...
Question 74: During the planning phase, the project manager meets with th...
Question 75: A project manager is attempting to establish the proper sequ...
Question 76: In which of the following categories does a business process...
Question 77: The project manager for a TV tower construction project rece...
Question 78: A project manager has noticed poor attendance at status meet...
Question 79: A small company has a successful proof of concept for an inn...
Question 80: A client has requested a project be completed ahead of sched...
Question 81: A project team is overseeing the installation of a new repti...
Question 82: A team has been assembled and assigned a project to reduce r...
Question 83: The project manager for a TV tower construction project rece...
Question 84: Which of the following events would MOST likely trigger comm...
Question 85: Which of the following job roles is primarily tasked with co...
Question 86: A sports event is coming to a local city, and the project ma...
Question 87: A new stakeholder has joined the project team and requested ...
Question 88: Which of the following is a characteristics of a matrix orga...
Question 89: A project has just finished performance testing and found th...
Question 90: A program manager informs a project manager that a new, high...
Question 91: A project manager is creating the WBS. In which of the follo...
Question 92: A team member learns that an assigned task is not due until ...
Question 93: A company has dictated project scope changes but has stated ...
Question 94: Which of the following are MOST essential to developing an e...
Question 95: A company hires an outside vendor to provide 24/7 support. W...
Question 96: A new high-priority project is assigned to the project manag...
Question 97: In which of the following organizational structures would a ...
Question 98: A client has provided a list of deliverables to include in t...
Question 99: Which of the following features describe a projectized organ...
Question 100: Which of the following are characteristics of a project? (Ch...
Question 101: A senior developer abruptly resigned without notice. Because...
Question 102: A project manager is successfully adhering to an eight-week ...
Question 103: There are four parallel paths on a network diagram. The summ...
Question 104: Two team members approach a project manager with different i...
Question 105: Which of the following risk strategies is represented by the...
Question 106: A team member has reported Task 3 will be completed ahead of...
Question 107: A project team member highlights to the project manager that...
Question 108: A new stake holder has joined the project team and requested...
Question 109: A project manager is working on a project, which needs to be...
Question 110: An active project has a CPI of 0.92. Which of the following ...
Question 111: A customer will have ongoing changes to project requirements...
Question 112: The client accepts the critical des.gn review Which of the f...
Question 113: Which of the following is a key aspect of the Agile project ...
Question 114: Language barriers will MOST likely influence a PM to:...
Question 115: A project manager is assigned to an ongoing project. Which o...
Question 116: A project manager is working on the project charter. Which o...
Question 117: Which of the following is a team-building stage that involve...
Question 118: A sponsor requests that the project team shorten the complet...
Question 119: A program manager informs a project manager that a new, high...
Question 120: A project manager is assigned to a new project that must sta...
Question 121: A project is nearing the expected completion date, but it is...
Question 122: During the execution phase, the project manager discovered t...
Question 123: There are four parallel paths on a network diagram. The summ...
Question 124: When a risk event occurs, which of the following documents i...
Question 125: A company hires an outside vendor to provide 24/7 support. W...
Question 126: The project manager was asked to provide recommendations for...
Question 127: The project manager for a TV tower construction project rece...
Question 128: In which of the fallowing organizational structures would a ...
Question 129: A WBS is being developed for a project. Which of the followi...
Question 130: The chairperson of the board is visiting from another countr...
Question 131: An organization has multiple projects that are taking place ...
Question 132: A project manager noticed the development team supporting a ...
Question 133: Which of the following are characteristics of a project? (Ch...
Question 134: Which of the following analyses should a project manager use...
Question 135: A project manager is assigned to a project and has not had a...
Question 136: A project manager noticed the development team supporting a ...
Question 137: Which of the following is a characteristics of a matrix orga...
Question 138: There are four parallel, paths on a network diagram. The sum...
Question 139: A project team received a memo stating no one can come into ...
Question 140: Tasks A and B have a duration of two days. Task A starts on ...
Question 141: A project manager provides status reports to a customer on a...
Question 142: A project manager has been assigned a project with a budget ...
Question 143: A company purchased a parachute supplier and is now sending ...
Question 144: A project has passed a phase-gate, and the new phase is read...
Question 145: Gas prices were included in the cost baseline for a transpor...
Question 146: A project team completed a brainstorming activity to determi...
Question 147: A project manager has an opportunity to add a highly skilled...
Question 148: Which of the following is a characteristics of a matrix orga...
Question 149: A software development project is struggling with a certain ...
Question 150: Two team members approach a project manager with different i...
Question 151: A project is taking more effort than anticipated. Which of t...
Question 152: A project manager would like to bring vendors into a new pro...
Question 153: Which of the following defines a group of projects that work...
Question 154: Which of the following is used to perform a root cause analy...
Question 155: Which of the following is a characteristic of a project?...
Question 156: Which of the following roles has approval authority for proj...
Question 157: Which of the following describes risk mitigation?...
Question 158: A project manager has identified a minor skills gap in the o...
Question 159: A project manager wants to introduce the practice of a WBS t...
Question 160: A project manager is creating the WBS. In which of the follo...
Question 161: A WBS is being developed for a project. Which of the followi...
Question 162: Which of the following documents does a vendor rely on to co...
Question 163: A project manager has been assigned a project with a budget ...
Question 164: The stakeholders who are available for the user acceptance t...
Question 165: A team member learns that an assigned task is not due until ...
Question 166: An agreement document that is intended to prevent two or mor...
Question 167: The project team has identified all the tasks needed to crea...
Question 168: In which of the following categories does a business process...
Question 169: A project team is showing off a new product prototype at a t...
Question 170: A project's key stakeholders have requested significant chan...
Question 171: A minor change to the baseline schedule is required. This ch...
Question 172: After identifying all known tasks, the project manager has s...
Question 173: A new high-priority project is assigned to the project manag...
Question 174: Assuming an iterative approach, which of the following will ...
Question 175: A company is hired to perform some of another organization's...
Question 176: An organization has determined that all projects must use a ...
Question 177: An active project has a CPI of 0.92. Which of the following ...
Question 178: A project sponsor approaches the project manager with a chan...
Question 179: A project team member highlights to the project manager that...
Question 180: A project manager is unsure if the quality of a deliverable ...
Question 181: A risk with a high probability and medium consequence to a p...
Question 182: An agreement document that is intended to prevent two or mor...
Question 183: Which of the following is a definition of an RFP?...
Question 184: While planning a project, the project team estimates known e...
Question 185: Which of the following is a key aspect of the Agile project ...
Question 186: In which of the following categories does a business process...
Question 187: Which of the following measurements would give the project m...
Question 188: A project manager was directed to complete a project sooner ...
Question 189: A busy project manager has a diverse set of stakeholders and...
Question 190: An agreement document that is intended to prevent two or mor...