Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 12/190

A project has activities on the critical path that must be completed before other activities can start.
Task A is dependent on Task C before Task D can be completed.
Task A requires task B to start.
Task B takes twice as long to complete as Task C.
Which of the following is the appropriate ordering of the critical path?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (190q)
Question 1: A project manager was directed to complete a project sooner ...
Question 2: A department manager asks a project manager about the status...
Question 3: Two team members completely disagree on how to complete a sp...
Question 4: A project has fallen behind schedule. Upon investigation, th...
Question 5: Which of the following are the components of a RACI matrix?...
Question 6: An external customer has requested a modification of the pro...
Question 7: The Chief Executive Officer (CEO) has announced that the har...
Question 8: During a project, the project manager discovers there is ins...
Question 9: A project team is identifying, rating the probability of, an...
Question 10: A project sponsor and Chief Information Officer (CIO) disagr...
Question 11: A vendor has accepted a proposed project from a customer. Wh...
Question 12: A project has activities on the critical path that must be c...
Question 13: The project schedule performance index is 1.1, and the cost ...
Question 14: A project manager who is part of a global team wants to have...
Question 15: A project team is composed of numerous team members who are ...
Question 16: A project team is comprised of a mix of in-house and virtual...
Question 17: The supervisor asks an engineer to be a project manager with...
Question 18: A project manager is successfully adhering to an eight-week ...
Question 19: A company has dictated project scope changes but has stated ...
Question 20: A project manager is successfully adhering to an eight-week ...
Question 21: There are four parallel paths on a network diagram. The summ...
Question 22: Given the following sprint: (Exhibit) Which of the following...
Question 23: A PM receives notification that an issue will impact a deliv...
Question 24: A project manager wants to introduce the practice of a WBS t...
Question 25: A project manager is determining a project's critical path t...
Question 26: While developing a project schedule, the project manager is ...
Question 27: A project has a BAC of $850,000. The project manager has ide...
Question 28: Which of the following risk strategies is represented by the...
Question 29: The chairperson of the board is visiting from another countr...
Question 30: An authorized change to a construction project was implement...
Question 31: A project manager is creating the monthly report for top man...
Question 32: Which of the following documents should be used FIRST when a...
Question 33: The PMO is responsible for: (Choose two.)...
Question 34: A project manager is mapping qualifications and available pe...
Question 35: A new project charter is being drafted. Which of the followi...
Question 36: An American publisher is participating in a workshop in Hong...
Question 37: New requirements were introduced during the execution phase ...
Question 38: Which of the following describes a burn rate?...
Question 39: A project requires daily status updates. Which of the follow...
Question 40: Which of the following activities are associated with the cl...
Question 41: According to the communication management plan, the project ...
Question 42: Tasks B and D start after Task A is completed. Task C starts...
Question 43: Two team members have concluded that documentation is not re...
Question 44: In which of the following organizational structures would a ...
Question 45: The project sponsor wishes to implement a 24/7 solution for ...
Question 46: An active project has a CPI of 0.92. Which of the following ...
Question 47: A non-stakeholder approaches the project manager and asks if...
Question 48: Which of the following is a characteristics of a matrix orga...
Question 49: An outsourced project team member approaches the project man...
Question 50: In a project with a BAC of $235,000, the CPI is 0.80, and th...
Question 51: A project manager is providing the lessons learned for a pro...
Question 52: A project manger received a change request, immediately docu...
Question 53: Which of the following is a characteristics of a matrix orga...
Question 54: A company hires an outside vendor to provide 24/7 support. W...
Question 55: During an ad-hoc meeting, the PM notifies the sponsor that w...
Question 56: A local company is part of a hostile takeover by a multinati...
Question 57: Two team members have concluded that documentation is not re...
Question 58: An active project is focused on quality assurance of the del...
Question 59: A risk with a high probability and medium consequence to a p...
Question 60: Project A is delivering the foundation for Project B. Constr...
Question 61: Which of the following measurements would give the project m...
Question 62: A project manager is creating the monthly report for top man...
Question 63: A project manager received a change request, immediately doc...
Question 64: The project schedule performance index is 1.1, and the cost ...
Question 65: Which of the following describes how a project is related to...
Question 66: After identifying all known tasks, the project manager has s...
Question 67: Which of the following is used to perform a root cause analy...
Question 68: A manager is reviewing some projects with two project manage...
Question 69: A project team is mainly based in a metropolitan area. The t...
Question 70: Which of the following are examples of organizational change...
Question 71: A project team is comprised of a mix of in-house and virtual...
Question 72: During a meeting, the project manager abruptly interrupts th...
Question 73: If a project sponsor wants to know the current status and pr...
Question 74: During the planning phase, the project manager meets with th...
Question 75: A project manager is attempting to establish the proper sequ...
Question 76: In which of the following categories does a business process...
Question 77: The project manager for a TV tower construction project rece...
Question 78: A project manager has noticed poor attendance at status meet...
Question 79: A small company has a successful proof of concept for an inn...
Question 80: A client has requested a project be completed ahead of sched...
Question 81: A project team is overseeing the installation of a new repti...
Question 82: A team has been assembled and assigned a project to reduce r...
Question 83: The project manager for a TV tower construction project rece...
Question 84: Which of the following events would MOST likely trigger comm...
Question 85: Which of the following job roles is primarily tasked with co...
Question 86: A sports event is coming to a local city, and the project ma...
Question 87: A new stakeholder has joined the project team and requested ...
Question 88: Which of the following is a characteristics of a matrix orga...
Question 89: A project has just finished performance testing and found th...
Question 90: A program manager informs a project manager that a new, high...
Question 91: A project manager is creating the WBS. In which of the follo...
Question 92: A team member learns that an assigned task is not due until ...
Question 93: A company has dictated project scope changes but has stated ...
Question 94: Which of the following are MOST essential to developing an e...
Question 95: A company hires an outside vendor to provide 24/7 support. W...
Question 96: A new high-priority project is assigned to the project manag...
Question 97: In which of the following organizational structures would a ...
Question 98: A client has provided a list of deliverables to include in t...
Question 99: Which of the following features describe a projectized organ...
Question 100: Which of the following are characteristics of a project? (Ch...
Question 101: A senior developer abruptly resigned without notice. Because...
Question 102: A project manager is successfully adhering to an eight-week ...
Question 103: There are four parallel paths on a network diagram. The summ...
Question 104: Two team members approach a project manager with different i...
Question 105: Which of the following risk strategies is represented by the...
Question 106: A team member has reported Task 3 will be completed ahead of...
Question 107: A project team member highlights to the project manager that...
Question 108: A new stake holder has joined the project team and requested...
Question 109: A project manager is working on a project, which needs to be...
Question 110: An active project has a CPI of 0.92. Which of the following ...
Question 111: A customer will have ongoing changes to project requirements...
Question 112: The client accepts the critical des.gn review Which of the f...
Question 113: Which of the following is a key aspect of the Agile project ...
Question 114: Language barriers will MOST likely influence a PM to:...
Question 115: A project manager is assigned to an ongoing project. Which o...
Question 116: A project manager is working on the project charter. Which o...
Question 117: Which of the following is a team-building stage that involve...
Question 118: A sponsor requests that the project team shorten the complet...
Question 119: A program manager informs a project manager that a new, high...
Question 120: A project manager is assigned to a new project that must sta...
Question 121: A project is nearing the expected completion date, but it is...
Question 122: During the execution phase, the project manager discovered t...
Question 123: There are four parallel paths on a network diagram. The summ...
Question 124: When a risk event occurs, which of the following documents i...
Question 125: A company hires an outside vendor to provide 24/7 support. W...
Question 126: The project manager was asked to provide recommendations for...
Question 127: The project manager for a TV tower construction project rece...
Question 128: In which of the fallowing organizational structures would a ...
Question 129: A WBS is being developed for a project. Which of the followi...
Question 130: The chairperson of the board is visiting from another countr...
Question 131: An organization has multiple projects that are taking place ...
Question 132: A project manager noticed the development team supporting a ...
Question 133: Which of the following are characteristics of a project? (Ch...
Question 134: Which of the following analyses should a project manager use...
Question 135: A project manager is assigned to a project and has not had a...
Question 136: A project manager noticed the development team supporting a ...
Question 137: Which of the following is a characteristics of a matrix orga...
Question 138: There are four parallel, paths on a network diagram. The sum...
Question 139: A project team received a memo stating no one can come into ...
Question 140: Tasks A and B have a duration of two days. Task A starts on ...
Question 141: A project manager provides status reports to a customer on a...
Question 142: A project manager has been assigned a project with a budget ...
Question 143: A company purchased a parachute supplier and is now sending ...
Question 144: A project has passed a phase-gate, and the new phase is read...
Question 145: Gas prices were included in the cost baseline for a transpor...
Question 146: A project team completed a brainstorming activity to determi...
Question 147: A project manager has an opportunity to add a highly skilled...
Question 148: Which of the following is a characteristics of a matrix orga...
Question 149: A software development project is struggling with a certain ...
Question 150: Two team members approach a project manager with different i...
Question 151: A project is taking more effort than anticipated. Which of t...
Question 152: A project manager would like to bring vendors into a new pro...
Question 153: Which of the following defines a group of projects that work...
Question 154: Which of the following is used to perform a root cause analy...
Question 155: Which of the following is a characteristic of a project?...
Question 156: Which of the following roles has approval authority for proj...
Question 157: Which of the following describes risk mitigation?...
Question 158: A project manager has identified a minor skills gap in the o...
Question 159: A project manager wants to introduce the practice of a WBS t...
Question 160: A project manager is creating the WBS. In which of the follo...
Question 161: A WBS is being developed for a project. Which of the followi...
Question 162: Which of the following documents does a vendor rely on to co...
Question 163: A project manager has been assigned a project with a budget ...
Question 164: The stakeholders who are available for the user acceptance t...
Question 165: A team member learns that an assigned task is not due until ...
Question 166: An agreement document that is intended to prevent two or mor...
Question 167: The project team has identified all the tasks needed to crea...
Question 168: In which of the following categories does a business process...
Question 169: A project team is showing off a new product prototype at a t...
Question 170: A project's key stakeholders have requested significant chan...
Question 171: A minor change to the baseline schedule is required. This ch...
Question 172: After identifying all known tasks, the project manager has s...
Question 173: A new high-priority project is assigned to the project manag...
Question 174: Assuming an iterative approach, which of the following will ...
Question 175: A company is hired to perform some of another organization's...
Question 176: An organization has determined that all projects must use a ...
Question 177: An active project has a CPI of 0.92. Which of the following ...
Question 178: A project sponsor approaches the project manager with a chan...
Question 179: A project team member highlights to the project manager that...
Question 180: A project manager is unsure if the quality of a deliverable ...
Question 181: A risk with a high probability and medium consequence to a p...
Question 182: An agreement document that is intended to prevent two or mor...
Question 183: Which of the following is a definition of an RFP?...
Question 184: While planning a project, the project team estimates known e...
Question 185: Which of the following is a key aspect of the Agile project ...
Question 186: In which of the following categories does a business process...
Question 187: Which of the following measurements would give the project m...
Question 188: A project manager was directed to complete a project sooner ...
Question 189: A busy project manager has a diverse set of stakeholders and...
Question 190: An agreement document that is intended to prevent two or mor...