Valid PK0-004 Dumps shared by ExamDiscuss.com for Helping Passing PK0-004 Exam! ExamDiscuss.com now offer the newest PK0-004 exam dumps, the ExamDiscuss.com PK0-004 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PK0-004 dumps with Test Engine here:

Access PK0-004 Dumps Premium Version
(797 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 38/152

Which of the following information does the project risk register typically contain?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (152q)
Question 1: A software development project is struggling with a certain ...
Question 2: A project manager is assigned to a project and has not had a...
Question 3: A project manager has updated the risk register with the cur...
Question 4: Resources for a project report to a project manager and a fu...
Question 5: A project team is defining detailed risks. Which of the foll...
Question 6: The chairperson of the board is visiting from another countr...
Question 7: A project manager needs to identify the resources assigned t...
Question 8: A team lead informs the project manager that the datacenter ...
Question 9: Which of the following defines the minimum level of engageme...
Question 10: Which of the following resources outlines consequences of no...
Question 11: Two team members are arguing over two different approaches t...
Question 12: Which of the following is the primary purpose of an MOA or a...
Question 13: A project's stakeholders have not been informed of project u...
Question 14: A project sponsor and Chief Information Officer (CIO) disagr...
Question 15: A change must be made to a project to comply with municipal ...
Question 16: A project manager is assigned to a project that was previous...
Question 17: Which of the following documents is typically signed by the ...
Question 18: A project manager was directed to complete a project sooner ...
Question 19: As a project processes, the team appears disjointed. Meeting...
Question 20: A project manager has noticed poor attendance as status meet...
Question 21: Which of the following describes some of the features of the...
Question 22: Which of the following is a team-building stage that involve...
Question 23: The project manager has noticed a vendor is not performing i...
Question 24: A project has passed a phase-gate, and the new phase is read...
Question 25: A project manager is assigned a project that is part of the ...
Question 26: A project manager does not have enough time to complete seve...
Question 27: When developing a project schedule, which of the following t...
Question 28: Which of the following project roles is ultimately responsib...
Question 29: A local company is part of a hostile takeover by a multinati...
Question 30: A key stakeholder asks the project manager for additional fe...
Question 31: Which of the following statements are correct regarding proj...
Question 32: A project team has just finished one phase of product develo...
Question 33: During the storming stage of a project team's development, i...
Question 34: Upon assignment to a project, the project manager is given a...
Question 35: During a project assessment, a project manager determines th...
Question 36: During the execution phase of a project, a project task has ...
Question 37: Which of the following documents are considered mutually bin...
Question 38: Which of the following information does the project risk reg...
Question 39: Before a team can start on a sprint, they will need to:...
Question 40: Which of the following techniques modifies the schedule base...
Question 41: Which of the following are characteristics of a project? (Ch...
Question 42: A company hires an outside vendor to provide 24/7 support. W...
Question 43: A new project manager is working in an environment where res...
Question 44: Gas prices were included in the cost baseline for a transpor...
Question 45: A project manager is justifying a required change with the a...
Question 46: A project manager is implementing a new edition of a magazin...
Question 47: A team member learns that an assigned task is not due until ...
Question 48: Which of the following is used to perform a root cause analy...
Question 49: A governance committee has just approved a new project. The ...
Question 50: Expenditure tracking helps with cost:...
Question 51: A task on the critical path has just been completed. The pro...
Question 52: The project manager has had a large number of change request...
Question 53: A team member was assigned a new task during a meeting. The ...
Question 54: Which of the following describes how a project is related to...
Question 55: A customer has stated that meeting the project schedule and ...
Question 56: Which of the following is a key aspect of the Agile project ...
Question 57: Which of the following network scheduling techniques is focu...
Question 58: Which of the following activity sequencing techniques uses n...
Question 59: A primary work location is unsafe due to a gas leak. The pro...
Question 60: Upper management asks a project sponsor to provide several a...
Question 61: A busy project manager has a diverse set of stakeholders and...
Question 62: A resource is assigned to two projects with two scheduled ta...
Question 63: A project manager is unsure if the quality of a deliverable ...
Question 64: A new stakeholder has requested the status and progress repo...
Question 65: The project schedule performance index is 1.1, and the cost ...
Question 66: An organization needs a vendor to provide a solution. The or...
Question 67: Which of the following provides tools and standard documenta...
Question 68: A project facilitator is working within a large project team...
Question 69: A project manager creates a Pareto chart based on the table ...
Question 70: Which of the following are MOST likely the responsibilities ...
Question 71: A project manager is required to maintain various documents ...
Question 72: Which of the following Agile ceremonies is used to determine...
Question 73: When an action is taken on a risk, which of the following is...
Question 74: Project status meetings have poor attendance. A SME from the...
Question 75: A project manager is managing a transactional project. One o...
Question 76: An organization has multiple projects that are taking place ...
Question 77: Which of the following should be included in an effective SO...
Question 78: A project manager is scheduling activities and determines on...
Question 79: The project sponsor wishes to implement a 24/7 solution for ...
Question 80: A small company has a successful proof of concept for an inn...
Question 81: The project team is distributed throughout a single country....
Question 82: If a project sponsor wants to know the current status and pr...
Question 83: Under an Agile methodology, standup meetings occur:...
Question 84: In a Scrum retrospective, which of the following categories ...
Question 85: A stakeholder wants to add four more data entry points on th...
Question 86: Which of the following metrics demonstrates to a project man...
Question 87: Two team members completely disagree on how to complete a sp...
Question 88: An organization has determined that all projects must use a ...
Question 89: An authorized change to a construction project was implement...
Question 90: A project manager is mapping qualifications and available pe...
Question 91: A company's management team is in a meeting to review all th...
Question 92: The PMO is confused by an entry in the risk register and wou...
Question 93: During a CCB, a SME evaluated the impact and provided new in...
Question 94: A project manager is attempting to establish the proper sequ...
Question 95: The project's network map has a loop with multiple project o...
Question 96: A project manager is creating the WBS. In which of the follo...
Question 97: Which of the following documents does a vendor rely on MOST ...
Question 98: Which of the following represents the order of the team deve...
Question 99: Communication on a project is flowing well. Team members are...
Question 100: A project encountered a problem and reached a milestone. In ...
Question 101: Assuming an iterative approach, which of the following will ...
Question 102: A project team on a four-year project has a shortage of work...
Question 103: A project team is composed of numerous team members who are ...
Question 104: A new stakeholder has joined the project team and requested ...
Question 105: A project manager is informed that a team member would like ...
Question 106: Which of the following documents should the project manager ...
Question 107: Which of the following tasks are responsibilities of the pro...
Question 108: Which of the following documents should be used FIRST when a...
Question 109: A PM receives notification that an issue will impact a deliv...
Question 110: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 111: In which of the following categories does a business process...
Question 112: A project team has finished creating a WBS and started devel...
Question 113: An agreement document that is intended to prevent two or mor...
Question 114: A project sponsor, project manager, and project facilitator ...
Question 115: A company has hired a new project manager. The PMO has brief...
Question 116: According to the communication management plan, the project ...
Question 117: A PM is reviewing bids from vendors and has a question. Whic...
Question 118: A project manager is determining a project's critical path t...
Question 119: Task B is not planned to start until Task A is completed. Ta...
Question 120: A post implementation review is being performed as a part of...
Question 121: A project manager is reviewing project performance. Which of...
Question 122: A subcontractor has submitted design documentation on the de...
Question 123: Which of the following is a reason for assessing risk in a p...
Question 124: The project team is moving from high-level risks to detailed...
Question 125: The executive sponsor asks a project manager to summarize th...
Question 126: A project team member highlights to the project manager that...
Question 127: A new project sponsor has joined the project team, and the c...
Question 128: A critical issue has developed in an active project, and the...
Question 129: A company has dictated project scope changes but has stated ...
Question 130: A project team has failed to deliver on changes the project ...
Question 131: A financial audit is being performed on a closed project. Wh...
Question 132: A project's key stakeholders have requested significant chan...
Question 133: Which of the following will identify the MOST potential proj...
Question 134: A project has activities on the critical path that must be c...
Question 135: Which of the following is the MOST important component again...
Question 136: A project manager has been assigned a complex project and do...
Question 137: Which of the following activity sequencing techniques uses n...
Question 138: Using Scrum, which of the following are discussed in a daily...
Question 139: The business stakeholder has been engaged late and has just ...
Question 140: A project has just finished performance testing and found th...
Question 141: A project manager would like to bring vendors into a new pro...
Question 142: Which of the following describes KPIs?...
Question 143: A team member was replaced on a project by a new team member...
Question 144: A project team added a new member who has proprietary inform...
Question 145: A department manager asks a project manager about the status...
Question 146: A project manager is not required to participate in performa...
Question 147: A new project charter is being drafted. Which of the followi...
Question 148: Which of the following documents will provide the MOST detai...
Question 149: After identifying all known tasks, the project manager has s...
Question 150: A vendor is unable to deliver an order by the specified date...
Question 151: A project team member states that the tasks identified in th...
Question 152: A PM has notified the project team of an immediate project r...