Question 51/152

A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (152q)
Question 1: A software development project is struggling with a certain ...
Question 2: A project manager is assigned to a project and has not had a...
Question 3: A project manager has updated the risk register with the cur...
Question 4: Resources for a project report to a project manager and a fu...
Question 5: A project team is defining detailed risks. Which of the foll...
Question 6: The chairperson of the board is visiting from another countr...
Question 7: A project manager needs to identify the resources assigned t...
Question 8: A team lead informs the project manager that the datacenter ...
Question 9: Which of the following defines the minimum level of engageme...
Question 10: Which of the following resources outlines consequences of no...
Question 11: Two team members are arguing over two different approaches t...
Question 12: Which of the following is the primary purpose of an MOA or a...
Question 13: A project's stakeholders have not been informed of project u...
Question 14: A project sponsor and Chief Information Officer (CIO) disagr...
Question 15: A change must be made to a project to comply with municipal ...
Question 16: A project manager is assigned to a project that was previous...
Question 17: Which of the following documents is typically signed by the ...
Question 18: A project manager was directed to complete a project sooner ...
Question 19: As a project processes, the team appears disjointed. Meeting...
Question 20: A project manager has noticed poor attendance as status meet...
Question 21: Which of the following describes some of the features of the...
Question 22: Which of the following is a team-building stage that involve...
Question 23: The project manager has noticed a vendor is not performing i...
Question 24: A project has passed a phase-gate, and the new phase is read...
Question 25: A project manager is assigned a project that is part of the ...
Question 26: A project manager does not have enough time to complete seve...
Question 27: When developing a project schedule, which of the following t...
Question 28: Which of the following project roles is ultimately responsib...
Question 29: A local company is part of a hostile takeover by a multinati...
Question 30: A key stakeholder asks the project manager for additional fe...
Question 31: Which of the following statements are correct regarding proj...
Question 32: A project team has just finished one phase of product develo...
Question 33: During the storming stage of a project team's development, i...
Question 34: Upon assignment to a project, the project manager is given a...
Question 35: During a project assessment, a project manager determines th...
Question 36: During the execution phase of a project, a project task has ...
Question 37: Which of the following documents are considered mutually bin...
Question 38: Which of the following information does the project risk reg...
Question 39: Before a team can start on a sprint, they will need to:...
Question 40: Which of the following techniques modifies the schedule base...
Question 41: Which of the following are characteristics of a project? (Ch...
Question 42: A company hires an outside vendor to provide 24/7 support. W...
Question 43: A new project manager is working in an environment where res...
Question 44: Gas prices were included in the cost baseline for a transpor...
Question 45: A project manager is justifying a required change with the a...
Question 46: A project manager is implementing a new edition of a magazin...
Question 47: A team member learns that an assigned task is not due until ...
Question 48: Which of the following is used to perform a root cause analy...
Question 49: A governance committee has just approved a new project. The ...
Question 50: Expenditure tracking helps with cost:...
Question 51: A task on the critical path has just been completed. The pro...
Question 52: The project manager has had a large number of change request...
Question 53: A team member was assigned a new task during a meeting. The ...
Question 54: Which of the following describes how a project is related to...
Question 55: A customer has stated that meeting the project schedule and ...
Question 56: Which of the following is a key aspect of the Agile project ...
Question 57: Which of the following network scheduling techniques is focu...
Question 58: Which of the following activity sequencing techniques uses n...
Question 59: A primary work location is unsafe due to a gas leak. The pro...
Question 60: Upper management asks a project sponsor to provide several a...
Question 61: A busy project manager has a diverse set of stakeholders and...
Question 62: A resource is assigned to two projects with two scheduled ta...
Question 63: A project manager is unsure if the quality of a deliverable ...
Question 64: A new stakeholder has requested the status and progress repo...
Question 65: The project schedule performance index is 1.1, and the cost ...
Question 66: An organization needs a vendor to provide a solution. The or...
Question 67: Which of the following provides tools and standard documenta...
Question 68: A project facilitator is working within a large project team...
Question 69: A project manager creates a Pareto chart based on the table ...
Question 70: Which of the following are MOST likely the responsibilities ...
Question 71: A project manager is required to maintain various documents ...
Question 72: Which of the following Agile ceremonies is used to determine...
Question 73: When an action is taken on a risk, which of the following is...
Question 74: Project status meetings have poor attendance. A SME from the...
Question 75: A project manager is managing a transactional project. One o...
Question 76: An organization has multiple projects that are taking place ...
Question 77: Which of the following should be included in an effective SO...
Question 78: A project manager is scheduling activities and determines on...
Question 79: The project sponsor wishes to implement a 24/7 solution for ...
Question 80: A small company has a successful proof of concept for an inn...
Question 81: The project team is distributed throughout a single country....
Question 82: If a project sponsor wants to know the current status and pr...
Question 83: Under an Agile methodology, standup meetings occur:...
Question 84: In a Scrum retrospective, which of the following categories ...
Question 85: A stakeholder wants to add four more data entry points on th...
Question 86: Which of the following metrics demonstrates to a project man...
Question 87: Two team members completely disagree on how to complete a sp...
Question 88: An organization has determined that all projects must use a ...
Question 89: An authorized change to a construction project was implement...
Question 90: A project manager is mapping qualifications and available pe...
Question 91: A company's management team is in a meeting to review all th...
Question 92: The PMO is confused by an entry in the risk register and wou...
Question 93: During a CCB, a SME evaluated the impact and provided new in...
Question 94: A project manager is attempting to establish the proper sequ...
Question 95: The project's network map has a loop with multiple project o...
Question 96: A project manager is creating the WBS. In which of the follo...
Question 97: Which of the following documents does a vendor rely on MOST ...
Question 98: Which of the following represents the order of the team deve...
Question 99: Communication on a project is flowing well. Team members are...
Question 100: A project encountered a problem and reached a milestone. In ...
Question 101: Assuming an iterative approach, which of the following will ...
Question 102: A project team on a four-year project has a shortage of work...
Question 103: A project team is composed of numerous team members who are ...
Question 104: A new stakeholder has joined the project team and requested ...
Question 105: A project manager is informed that a team member would like ...
Question 106: Which of the following documents should the project manager ...
Question 107: Which of the following tasks are responsibilities of the pro...
Question 108: Which of the following documents should be used FIRST when a...
Question 109: A PM receives notification that an issue will impact a deliv...
Question 110: Risk ID 2 has occurred. (Exhibit) Which of the following way...
Question 111: In which of the following categories does a business process...
Question 112: A project team has finished creating a WBS and started devel...
Question 113: An agreement document that is intended to prevent two or mor...
Question 114: A project sponsor, project manager, and project facilitator ...
Question 115: A company has hired a new project manager. The PMO has brief...
Question 116: According to the communication management plan, the project ...
Question 117: A PM is reviewing bids from vendors and has a question. Whic...
Question 118: A project manager is determining a project's critical path t...
Question 119: Task B is not planned to start until Task A is completed. Ta...
Question 120: A post implementation review is being performed as a part of...
Question 121: A project manager is reviewing project performance. Which of...
Question 122: A subcontractor has submitted design documentation on the de...
Question 123: Which of the following is a reason for assessing risk in a p...
Question 124: The project team is moving from high-level risks to detailed...
Question 125: The executive sponsor asks a project manager to summarize th...
Question 126: A project team member highlights to the project manager that...
Question 127: A new project sponsor has joined the project team, and the c...
Question 128: A critical issue has developed in an active project, and the...
Question 129: A company has dictated project scope changes but has stated ...
Question 130: A project team has failed to deliver on changes the project ...
Question 131: A financial audit is being performed on a closed project. Wh...
Question 132: A project's key stakeholders have requested significant chan...
Question 133: Which of the following will identify the MOST potential proj...
Question 134: A project has activities on the critical path that must be c...
Question 135: Which of the following is the MOST important component again...
Question 136: A project manager has been assigned a complex project and do...
Question 137: Which of the following activity sequencing techniques uses n...
Question 138: Using Scrum, which of the following are discussed in a daily...
Question 139: The business stakeholder has been engaged late and has just ...
Question 140: A project has just finished performance testing and found th...
Question 141: A project manager would like to bring vendors into a new pro...
Question 142: Which of the following describes KPIs?...
Question 143: A team member was replaced on a project by a new team member...
Question 144: A project team added a new member who has proprietary inform...
Question 145: A department manager asks a project manager about the status...
Question 146: A project manager is not required to participate in performa...
Question 147: A new project charter is being drafted. Which of the followi...
Question 148: Which of the following documents will provide the MOST detai...
Question 149: After identifying all known tasks, the project manager has s...
Question 150: A vendor is unable to deliver an order by the specified date...
Question 151: A project team member states that the tasks identified in th...
Question 152: A PM has notified the project team of an immediate project r...