A procurement manager is sourcing some high-value equipment for their organisation. What are the elements comprising whole-life costing that they need to consider?
Correct Answer: A
Whole-life costing includes all costs from acquisition to disposal, ensuring comprehensive financial planning. Essential components include: * Acquisition and purchase costs: Initial costs incurred to procure the equipment. * Usage costs: Operational expenses, including energy and consumables. * End-of-life costs: Disposal, recycling, or decommissioning expenses. Whole-life asset management aims to minimize these costs over an asset's lifecycle, ensuring value and performance.