Valid L4M6 Dumps shared by ExamDiscuss.com for Helping Passing L4M6 Exam! ExamDiscuss.com now offer the newest L4M6 exam dumps, the ExamDiscuss.com L4M6 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com L4M6 dumps with Test Engine here:
Under what circumstances should a competitive tender not be completed? Select TWO.
Correct Answer: B,D
Note the word 'NOT' in the question. In order for a competitive tender to be successful, there should be a clear specification in place (i.e. you need to know what you want, in order for suppliers to bid for it). Competitive tendering should also only be used for high value purchases; it's time consuming to do, so you wouldn't do it for low value items such as pens for the office. Therefore the correct answer to this question is 'items are of low value' and 'there isn't a clear specification'. There's a useful table on p.73 of when you would and wouldn't use a competitive tender.