Lee is a procurement manager at Real Pirates Ltd and he has a contract with Peg Leg Industries for the supply of fake, wooden legs for his team of Pirates. Real Pirates Ltd have been working with Peg Leg Industries for almost 10 years but recently Lee has discovered he will need to terminate the contract due to 'Contract Frustration'. What could be the reason for this?
Correct Answer: B
The correct answer is 'An unexpected incident has occurred beyond anyone's control'. A good example of this would be the Covid-19 pandemic- neither the buyer nor supplier could have predicted this, and if this means that the contract can't be completed - then the contract can be terminated (in the UK at least). A way to avoid this would be to include a Force Majeur clause listing possible circumstances that could occur. When there's a Force Majeur clause, these eventualities are now classed as foreseen rather than unforeseen. See p.108