Question 7/15

You ate in a backlog refinement meeting with the development team and the product owner. You review a story for an integration Involving a third-party system. A payload will be sent from the Appian system through the integration to the third-party system. The story is 21 points on a Fibonacci scale, and requires development from your Appian learn, as well as the technical resources from the third-party system. This item is crucial to your project s success.
What are the two recommended steps to ensure this story can be developed effectively?