<< Prev Question Next Question >>

Question 53/82

Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (82q)
Question 1: What activities are concurrent to Activity 2001 in the "norm...
Question 2: When resource leveling craft labor for a critical path sched...
Question 3: For which of these delays should an owner grant a time exten...
Question 4: Using the "normal" schedule, and assuming you are billing on...
Question 5: If a cost estimate assumes that 240 hours will be expended o...
Question 6: What is a critical path method schedule?...
Question 7: Which letter of the alphabet best approximates the graphical...
Question 8: Midway through the project you received an executed change o...
Question 9: Total float is defined as the amount of time an activity can...
Question 10: Identify the late finish to develop plans and specs. (Exhibi...
Question 11: Which of the following project planning situations is the mo...
Question 12: The sum of all budgets for work scheduled to be accomplished...
Question 13: Project schedules help control all of the following EXCEPT f...
Question 14: As a change to the network for the current update, activity ...
Question 15: Using the "normal" schedule, given Activity 3001 and the rel...
Question 16: These are the activities on the critical path: (Exhibit)...
Question 17: The BEST reason to use multiple calendars is to:...
Question 18: The work breakdown structure is used to organize...
Question 19: What project cost elements would NOT normally be reflected i...
Question 20: Which of the following is NOT a tool or technique used to pe...
Question 21: An earned value-based project control system can use either ...
Question 22: Select the most appropriate explanation for use of a winter/...
Question 23: Using the normal schedule, given Activity 3001 and the relat...
Question 24: An early start constraint dictates...
Question 25: Which of the following are NOT considerations or constraints...
Question 26: Using the "crashed" schedule, if you start Activity 2002 on ...
Question 27: Theoretically construct a summary activity for activities 60...
Question 28: When reconstructing a CPM schedule electronically from a har...
Question 29: Assumptions made during the planning stage should be________...
Question 30: Which of the following will always describe the critical pat...
Question 31: By subtracting a measured unit productivity rate during an i...
Question 32: What is the remaining work duration of Active D? (Exhibit)...
Question 33: What is the primary difference between the arrow diagramming...
Question 34: What portion of Activity B is on the critical path?...
Question 35: If no time extensions are granted and all actual delays are ...
Question 36: What changes to logic would eliminate Activity B from the cr...
Question 37: Which of the following risks CANNOT be estimated by BILCO wi...
Question 38: During proofing of the product manual, a problem was discove...
Question 39: Determine the driving activity for Activity 10001. (Exhibit)...
Question 40: How could the structural steel drawing delay have been preve...
Question 41: Which of the following are NOT normally included in the proj...
Question 42: Free float is the
Question 43: At the end of month one, did the delay to the parking struct...
Question 44: You are retained by a contractor who asks you to perform a s...
Question 45: What method would be the best way to determine the most like...
Question 46: Which of the following is NOT required when initially planni...
Question 47: Which of the following will NOT affect the total float calcu...
Question 48: SUBCO is a potential concrete bridge contractor based in a m...
Question 49: Assuming that you had only one crane capable of 30 lifts per...
Question 50: Which of the following statements is true?...
Question 51: The addition of which of the following relationships would c...
Question 52: Background Your name is Evan Marshal. You are the corporate ...
Question 53: Using the "normal" schedule, theoretically construct a hammo...
Question 54: Considering the information provided for the project, what i...
Question 55: Activity C is a
Question 56: What method offers the best chance of the schedule being use...
Question 57: Determine the correct formula and date for the late start fo...
Question 58: Which statement is true?
Question 59: All the following describe the critical path of a schedule E...
Question 60: Which of the following phases does NOT describe the commonly...
Question 61: Estimate to complete (ETC) is __________________....
Question 62: Determine the correct formula and date for the late finish f...
Question 63: Determine the correct formula and date for the late finish f...
Question 64: Budgeted cost of work scheduled is _______________________....
Question 65: Which of the following is NOT input data to the construction...
Question 66: How much Total Float does drafting the product manual have? ...
Question 67: Theoretically construct a summary activity for activities 20...
Question 68: What is accurate about Activity 7001 in the precedence diagr...
Question 69: If Activity A was delayed 5 days from starting, which of the...
Question 70: A driving relationship is _____________________....
Question 71: In analyzing a logical chain of activities in a critical pat...
Question 72: Activity 1001 started on the scheduled date but has slipped ...
Question 73: Which of these letters, symbols or words best approximates t...
Question 74: How many work days does it take to move the product from tes...
Question 75: The linear scheduling velocity diagram has the following two...
Question 76: Using the "normal" schedule, what is the early finish date o...
Question 77: Who will receive the most benefit from a master schedule of ...
Question 78: Is activity 7001 pictured correctly in the precedence diagra...
Question 79: Determine the correct formula and date for the late finish f...
Question 80: If after calculating a schedule an activity exhibits negativ...
Question 81: Each of the following accurately describes total float in a ...
Question 82: If a detailed estimate is NOT available to assist in the for...