Background
Your name is Evan Marshal. You are the corporate scheduler for Happy Insurance Corporation (HIC), a general health insurance company located in Ridgemond, Illinois. HIC is very busy with 49 unique software development projects. The organization structure at HIC gives the project scheduling responsibility to the Project Manager assigned to each project. You are charged with coordination of the project schedules into a Master Schedule and quality control for scheduling on the individual development projects. You report directly to the Director of Information Services (DIS), Desmond Rayburn.
It has come to your attention Project JP-114 has fallen behind schedule and Rita Belateau, the Project Manager, wants to accelerate the project in order to reclaim lost time. Rita is a strong supporter of Total Quality Management and strives for zero failures; therefore she is assessing the need for overtime for resources assigned to an activity that is not projecting a completion prior to the early finish depicted in the current schedule.
You and Rita review the current schedule to identify which activities are on the critical path and which activities have plenty of float. The review reveals several activities have suffered less than planned productivity and have contributed to falling behind. In the process of this review, you and Rita also review the budget for Project JP-114 and notice not only the schedule has fallen behind but the cost to date is more than she had expected. To total budget is $150,000, planned to date is $30,000; expended to date is $37,000.
With nine months remaining until baseline contract completion, Rita needs to bring Project JP-114 back on track; knowing overtime for an extended period of time is not always the right answer, especially with the cost to date already over planned.
In order to truly understand the options available to help remedy the current situation, you and Rita brainstorm on several potential courses of action. All the potential courses of action will require an evaluation of budget impact versus schedule correction.
1. Pull the project team together and ensure everyone understands which activities are on the critical path.
Rita would like to use the existing project team and focus them on these critical path activities, laying out a plan for periodic overtime when needed to crunch through a deliverable. This approach could add approximately 20% to the budget.
2. Outsource various modules of activities to qualified and known consultants. This could drive up the costs and must be evaluated before implemented. Having an outside source working in parallel with the project team could also accelerate the schedule to mitigate some of the delays, as well as keep overtime down to a minimum for the project team. Potentially this could add as much as 40% to the budget, but could also be very productive schedule wise.
3. Mandatory overtime for the project team - entire project goes on a 50-hour work week. If the entire project team works overtime for an extended period of time, the budget could see an additional 60% increase.
4. The project continues as is completes the project late and accepts the penalties imposed. Penalties imposed for late delivery could add as much as 50% to the budget.
Assignment
Draft a proper memorandum to Desmond Raybum, IS Director, explaining in your own words:
a). the current problem and potential impact(s);
b). each course of action, stating advantages and disadvantages as appropriate;
c). your recommendations, properly supported.
Please be sure to include the rationale for your recommendations. Be sure to summarize your thoughts and address (To, From, Date, and Subject/Project Name) and close the memo appropriately. If you are uncomfortable with the courses of action noted, provide your own with appropriate substantiation for your position. Limit your answer to one, full typewritten page (roughly three handwritten pages).
While your email can be a detailed as you like, be sure to write sufficiently to address each element of the assignment, yet not so long that you go beyond the scope of the exercise.
Take time to read the problem and consider what you want Evan to say. Good luck!

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (82q)
Question 1: What activities are concurrent to Activity 2001 in the "norm...
Question 2: When resource leveling craft labor for a critical path sched...
Question 3: For which of these delays should an owner grant a time exten...
Question 4: Using the "normal" schedule, and assuming you are billing on...
Question 5: If a cost estimate assumes that 240 hours will be expended o...
Question 6: What is a critical path method schedule?...
Question 7: Which letter of the alphabet best approximates the graphical...
Question 8: Midway through the project you received an executed change o...
Question 9: Total float is defined as the amount of time an activity can...
Question 10: Identify the late finish to develop plans and specs. (Exhibi...
Question 11: Which of the following project planning situations is the mo...
Question 12: The sum of all budgets for work scheduled to be accomplished...
Question 13: Project schedules help control all of the following EXCEPT f...
Question 14: As a change to the network for the current update, activity ...
Question 15: Using the "normal" schedule, given Activity 3001 and the rel...
Question 16: These are the activities on the critical path: (Exhibit)...
Question 17: The BEST reason to use multiple calendars is to:...
Question 18: The work breakdown structure is used to organize...
Question 19: What project cost elements would NOT normally be reflected i...
Question 20: Which of the following is NOT a tool or technique used to pe...
Question 21: An earned value-based project control system can use either ...
Question 22: Select the most appropriate explanation for use of a winter/...
Question 23: Using the normal schedule, given Activity 3001 and the relat...
Question 24: An early start constraint dictates...
Question 25: Which of the following are NOT considerations or constraints...
Question 26: Using the "crashed" schedule, if you start Activity 2002 on ...
Question 27: Theoretically construct a summary activity for activities 60...
Question 28: When reconstructing a CPM schedule electronically from a har...
Question 29: Assumptions made during the planning stage should be________...
Question 30: Which of the following will always describe the critical pat...
Question 31: By subtracting a measured unit productivity rate during an i...
Question 32: What is the remaining work duration of Active D? (Exhibit)...
Question 33: What is the primary difference between the arrow diagramming...
Question 34: What portion of Activity B is on the critical path?...
Question 35: If no time extensions are granted and all actual delays are ...
Question 36: What changes to logic would eliminate Activity B from the cr...
Question 37: Which of the following risks CANNOT be estimated by BILCO wi...
Question 38: During proofing of the product manual, a problem was discove...
Question 39: Determine the driving activity for Activity 10001. (Exhibit)...
Question 40: How could the structural steel drawing delay have been preve...
Question 41: Which of the following are NOT normally included in the proj...
Question 42: Free float is the
Question 43: At the end of month one, did the delay to the parking struct...
Question 44: You are retained by a contractor who asks you to perform a s...
Question 45: What method would be the best way to determine the most like...
Question 46: Which of the following is NOT required when initially planni...
Question 47: Which of the following will NOT affect the total float calcu...
Question 48: SUBCO is a potential concrete bridge contractor based in a m...
Question 49: Assuming that you had only one crane capable of 30 lifts per...
Question 50: Which of the following statements is true?...
Question 51: The addition of which of the following relationships would c...
Question 52: Background Your name is Evan Marshal. You are the corporate ...
Question 53: Using the "normal" schedule, theoretically construct a hammo...
Question 54: Considering the information provided for the project, what i...
Question 55: Activity C is a
Question 56: What method offers the best chance of the schedule being use...
Question 57: Determine the correct formula and date for the late start fo...
Question 58: Which statement is true?
Question 59: All the following describe the critical path of a schedule E...
Question 60: Which of the following phases does NOT describe the commonly...
Question 61: Estimate to complete (ETC) is __________________....
Question 62: Determine the correct formula and date for the late finish f...
Question 63: Determine the correct formula and date for the late finish f...
Question 64: Budgeted cost of work scheduled is _______________________....
Question 65: Which of the following is NOT input data to the construction...
Question 66: How much Total Float does drafting the product manual have? ...
Question 67: Theoretically construct a summary activity for activities 20...
Question 68: What is accurate about Activity 7001 in the precedence diagr...
Question 69: If Activity A was delayed 5 days from starting, which of the...
Question 70: A driving relationship is _____________________....
Question 71: In analyzing a logical chain of activities in a critical pat...
Question 72: Activity 1001 started on the scheduled date but has slipped ...
Question 73: Which of these letters, symbols or words best approximates t...
Question 74: How many work days does it take to move the product from tes...
Question 75: The linear scheduling velocity diagram has the following two...
Question 76: Using the "normal" schedule, what is the early finish date o...
Question 77: Who will receive the most benefit from a master schedule of ...
Question 78: Is activity 7001 pictured correctly in the precedence diagra...
Question 79: Determine the correct formula and date for the late finish f...
Question 80: If after calculating a schedule an activity exhibits negativ...
Question 81: Each of the following accurately describes total float in a ...
Question 82: If a detailed estimate is NOT available to assist in the for...