Valid CPIM-8.0 Dumps shared by ExamDiscuss.com for Helping Passing CPIM-8.0 Exam! ExamDiscuss.com now offer the newest CPIM-8.0 exam dumps, the ExamDiscuss.com CPIM-8.0 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CPIM-8.0 dumps with Test Engine here:
The cost accountant has discovered a consistent overage in actual run time for one operation. This information should be sent first to the:
Correct Answer: C
The production supervisor is the most appropriate person to send the information about the overage in actual run time for one operation. The production supervisor is responsible for overseeing the execution of the production plan and ensuring that the operations are performed efficiently and effectively. The production supervisor can review the actual run time data and compare it with the planned run time, identify the possible causes of the overage, and take corrective actions if needed. The production supervisor can also explain the overage to the cost accountant and other stakeholders, such as the product manager, the quality manager, and the engineering manager, and provide feedback for improving the planning and routing of the operation. References: APICS CPIM Part 2 Exam Content Manual, p. 30 [APICS CPIM Learning System Version 8.0], Module 4, Section D, p. 4-35