Valid CPIM-8.0 Dumps shared by ExamDiscuss.com for Helping Passing CPIM-8.0 Exam! ExamDiscuss.com now offer the newest CPIM-8.0 exam dumps, the ExamDiscuss.com CPIM-8.0 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com CPIM-8.0 dumps with Test Engine here:
How would a master production schedule (MPS) be used In an assemble-to-order (ATO) manufacturing environment?
Correct Answer: A
In an assemble-to-order (ATO) manufacturing environment, the MPS is used to plan subassemblies and components that have long lead times or high demand variability. These subassemblies and components are produced and stocked in anticipation of customer orders. The end items are only scheduled in the MPS when a customer order is received, and they are assembled from the available subassemblies and components. This reduces the lead time and inventory for the end items, while increasing the flexibility and responsiveness to customer needs. ATO is a hybrid strategy between make-to-stock (MTS) and make-to-order (MTO). References := * CPIM Exam Content Manual, Module 4: Supply, Section 4.1: Master Production Schedule, p. 14 * Manufacturing Planning and Control for Supply Chain Management, Chapter 8: Master Production Scheduling, Section 8.3: Master Production Scheduling in Different Environments, pp. 191-192