Which planning document includes activities designed to drive the behavior of those impacted by a change initiative?
Correct Answer: A
Thestakeholder engagement planoutlines activities to influence, support, and drive the behavior of stakeholders impacted by the change. ACMP highlights that adoption is driven byinvolvement, reinforcement, and targeted interventions. Sponsorship plans (B) define leader roles, transition plans (C) focus on operational handoffs, and resource plans (D) address capacity. Only the stakeholder engagement plan (A) directly specifiesbehavior-driving activitiesfor adoption.
(Reference: ACMP Standard, Process Group 3 - Stakeholder Engagement Plan; Purpose: Define activities to influence and drive stakeholder behavior.)