<< Prev Question Next Question >>

Question 74/75

You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (75q)
Question 1: Constraints control events or activities that ______________...
Question 2: What day would Activity C complete if the duration of Activi...
Question 3: In a graphical earned value analysis, what time-scaled value...
Question 4: By subtracting a measured unit productivity rate during an i...
Question 5: Resource planning must take all of the following into accoun...
Question 6: Determine the correct formula and date for the late finish f...
Question 7: Which of the following will NOT affect the total float calcu...
Question 8: Crane operators require 1 hour prep and 1 hour clean-up and ...
Question 9: A driving relationship is _____________________....
Question 10: Assuming that you had only one crane capable of 30 lifts per...
Question 11: When reconstructing a CPM schedule electronically from a har...
Question 12: What portion of Activity B is on the critical path?...
Question 13: Using the "normal" schedule, and assuming you are billing on...
Question 14: Which of the following types of delay will NOT result in a t...
Question 15: Theoretically construct a summary activity for activities 20...
Question 16: What is the result of a forward pass calculation?...
Question 17: During proofing of the product manual, a problem was discove...
Question 18: What day would Activity C complete if the duration of Activi...
Question 19: Who will receive the most benefit from a master schedule of ...
Question 20: If drafting of the product manual overruns its planned durat...
Question 21: During proofing of the product manual, a problem was discove...
Question 22: Determine the correct formula and date for the late finish f...
Question 23: Which of the following is NOT input data to the construction...
Question 24: Which letter of the alphabet best approximates the graphical...
Question 25: What is the primary difference between the arrow diagramming...
Question 26: In an earned value-based system, a schedule performance inde...
Question 27: Which of the following is NOT a tool or technique used to pe...
Question 28: What project cost elements would NOT normally be reflected i...
Question 29: All the following describe the critical path of a schedule E...
Question 30: When using a detailed estimate as the basis for work package...
Question 31: Prior to the beginning work on Activity 6001, the scope is c...
Question 32: At a minimum, periodic reporting must be done at what interv...
Question 33: What is accurate about Activity 7001 in the precedence diagr...
Question 34: Using the crashed schedule, if you start Activity 2002 on 12...
Question 35: In analyzing a logical chain of activities in a critical pat...
Question 36: Which of the following is NOT required when performing weekl...
Question 37: At the end of month one, did the delay to the parking struct...
Question 38: If the administrative constraints for developing the precede...
Question 39: Which activity is drawn in the incorrect position? (Exhibit)...
Question 40: Using the normal schedule, what is the owner's total cost of...
Question 41: What is a key first step in developing a critical path metho...
Question 42: Determine the correct formula and date for the late finish f...
Question 43: Using the normal schedule, given Activity 3001 and the relat...
Question 44: Using the normal schedule, what is the early finish date and...
Question 45: If a new hammock activity covering activities 6001 through 6...
Question 46: The amount of time that an activity can be delayed from its ...
Question 47: When resource leveling craft labor for a critical path sched...
Question 48: What is the remaining work duration of Active D? (Exhibit)...
Question 49: Which of the following risks CANNOT be estimated by BILCO wi...
Question 50: Which of the following phases does NOT describe the commonly...
Question 51: What method offers the best chance of the schedule being use...
Question 52: What is the workweek period for this project? (Exhibit)...
Question 53: The BEST reason to use multiple calendars is to:...
Question 54: If a cost estimate assumes that 240 hours will be expended o...
Question 55: Activity C is a
Question 56: Assuming conventional finish-to-start relationships, to calc...
Question 57: If no time extensions are granted and all actual delays are ...
Question 58: What owner action could have mitigated the late completion o...
Question 59: Which of the following is NOT required when initially planni...
Question 60: Assuming a total of 30 lifts per crane per day, what is the ...
Question 61: An early start constraint dictates...
Question 62: The expected remaining cost needed to complete an activity, ...
Question 63: Why does activity 1001 have two successor activities? (Exhib...
Question 64: If Activity A was delayed 5 days from starting, which of the...
Question 65: Time-scaled logic diagrams are
Question 66: As a change to the network for the current update, activity ...
Question 67: If someone wanted to constrain a project's end date so that ...
Question 68: In its simplest form, what is the main drawback of critical ...
Question 69: What activities are concurrent to Activity 2001 in the "norm...
Question 70: Considering the information provided for the project, what i...
Question 71: Which of the following parties is NOT a stakeholder of the S...
Question 72: Is activity 7001 pictured correctly in the precedence diagra...
Question 73: Which of the following statements is true?...
Question 74: You are developing a detailed critical path schedule for a p...
Question 75: Which statement is true?