Valid AACE-PSP Dumps shared by ExamDiscuss.com for Helping Passing AACE-PSP Exam! ExamDiscuss.com now offer the newest AACE-PSP exam dumps, the ExamDiscuss.com AACE-PSP exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com AACE-PSP dumps with Test Engine here:

Access AACE-PSP Dumps Premium Version
(165 Q&As Dumps, 35%OFF Special Discount Code: freecram)

Online Access Free AACE-PSP Exam Questions

Exam Code:AACE-PSP
Exam Name:Planning & Scheduling Professional (PSP) Exam
Certification Provider:AACE International
Free Question Number:75
Version:v2025-06-14
Rating:
# of views:224
# of Questions views:2720
Go To AACE-PSP Questions

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Other Version
1112 viewsAACEInternational.AACE-PSP.v2022-05-10.q39
Exam Question List
Question 1: Constraints control events or activities that ______________...
Question 2: What day would Activity C complete if the duration of Activi...
Question 3: In a graphical earned value analysis, what time-scaled value...
Question 4: By subtracting a measured unit productivity rate during an i...
Question 5: Resource planning must take all of the following into accoun...
Question 6: Determine the correct formula and date for the late finish f...
Question 7: Which of the following will NOT affect the total float calcu...
Question 8: Crane operators require 1 hour prep and 1 hour clean-up and ...
Question 9: A driving relationship is _____________________....
Question 10: Assuming that you had only one crane capable of 30 lifts per...
Question 11: When reconstructing a CPM schedule electronically from a har...
Question 12: What portion of Activity B is on the critical path?...
Question 13: Using the "normal" schedule, and assuming you are billing on...
Question 14: Which of the following types of delay will NOT result in a t...
Question 15: Theoretically construct a summary activity for activities 20...
Question 16: What is the result of a forward pass calculation?...
Question 17: During proofing of the product manual, a problem was discove...
Question 18: What day would Activity C complete if the duration of Activi...
Question 19: Who will receive the most benefit from a master schedule of ...
Question 20: If drafting of the product manual overruns its planned durat...
Question 21: During proofing of the product manual, a problem was discove...
Question 22: Determine the correct formula and date for the late finish f...
Question 23: Which of the following is NOT input data to the construction...
Question 24: Which letter of the alphabet best approximates the graphical...
Question 25: What is the primary difference between the arrow diagramming...
Question 26: In an earned value-based system, a schedule performance inde...
Question 27: Which of the following is NOT a tool or technique used to pe...
Question 28: What project cost elements would NOT normally be reflected i...
Question 29: All the following describe the critical path of a schedule E...
Question 30: When using a detailed estimate as the basis for work package...
Question 31: Prior to the beginning work on Activity 6001, the scope is c...
Question 32: At a minimum, periodic reporting must be done at what interv...
Question 33: What is accurate about Activity 7001 in the precedence diagr...
Question 34: Using the crashed schedule, if you start Activity 2002 on 12...
Question 35: In analyzing a logical chain of activities in a critical pat...
Question 36: Which of the following is NOT required when performing weekl...
Question 37: At the end of month one, did the delay to the parking struct...
Question 38: If the administrative constraints for developing the precede...
Question 39: Which activity is drawn in the incorrect position? (Exhibit)...
Question 40: Using the normal schedule, what is the owner's total cost of...
Question 41: What is a key first step in developing a critical path metho...
Question 42: Determine the correct formula and date for the late finish f...
Question 43: Using the normal schedule, given Activity 3001 and the relat...
Question 44: Using the normal schedule, what is the early finish date and...
Question 45: If a new hammock activity covering activities 6001 through 6...
Question 46: The amount of time that an activity can be delayed from its ...
Question 47: When resource leveling craft labor for a critical path sched...
Question 48: What is the remaining work duration of Active D? (Exhibit)...
Question 49: Which of the following risks CANNOT be estimated by BILCO wi...
Question 50: Which of the following phases does NOT describe the commonly...
Question 51: What method offers the best chance of the schedule being use...
Question 52: What is the workweek period for this project? (Exhibit)...
Question 53: The BEST reason to use multiple calendars is to:...
Question 54: If a cost estimate assumes that 240 hours will be expended o...
Question 55: Activity C is a
Question 56: Assuming conventional finish-to-start relationships, to calc...
Question 57: If no time extensions are granted and all actual delays are ...
Question 58: What owner action could have mitigated the late completion o...
Question 59: Which of the following is NOT required when initially planni...
Question 60: Assuming a total of 30 lifts per crane per day, what is the ...
Question 61: An early start constraint dictates...
Question 62: The expected remaining cost needed to complete an activity, ...
Question 63: Why does activity 1001 have two successor activities? (Exhib...
Question 64: If Activity A was delayed 5 days from starting, which of the...
Question 65: Time-scaled logic diagrams are
Question 66: As a change to the network for the current update, activity ...
Question 67: If someone wanted to constrain a project's end date so that ...
Question 68: In its simplest form, what is the main drawback of critical ...
Question 69: What activities are concurrent to Activity 2001 in the "norm...
Question 70: Considering the information provided for the project, what i...
Question 71: Which of the following parties is NOT a stakeholder of the S...
Question 72: Is activity 7001 pictured correctly in the precedence diagra...
Question 73: Which of the following statements is true?...
Question 74: You are developing a detailed critical path schedule for a p...
Question 75: Which statement is true?