Valid 5V0-21.20 Dumps shared by EduDump.com for Helping Passing 5V0-21.20 Exam! EduDump.com now offer the newest 5V0-21.20 exam dumps, the EduDump.com 5V0-21.20 exam questions have been updated and answers have been corrected get the newest EduDump.com 5V0-21.20 dumps with Test Engine here:
A vSAN administrator is working on a 4 host homogenous vSAN Cluster that has 2 disk groups per host. One of the hosts needs to be permanently removed and repurposed for some other use. These are the out of order steps which need to be completed: 1. Delete the disk group(s) that reside on the host you want to decommission. 2. Wait for resync traffic to complete and the host to enter maintenance mode. 3. Ensure there is sufficient capacity in the vSAN disk groups to decommission a node. 4. Put the host into maintenance mode with full data migration selected. 5. Move the ESXi host out of the cluster. What is the correct order?