Valid LEED-AP-ID-C Dumps shared by ExamDiscuss.com for Helping Passing LEED-AP-ID-C Exam! ExamDiscuss.com now offer the newest LEED-AP-ID-C exam dumps, the ExamDiscuss.com LEED-AP-ID-C exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com LEED-AP-ID-C dumps with Test Engine here:
Based on the results of a six-hour waste stream study, the team for an Interior Design and Construction Retail project plans to provide dedicated areas for four recyclable waste streams: cardboard, plastic, metal, and paper. The project is open to the public 10 hours a day, six days a week. Which of the following actions should be the project team's top priority in order to demonstrate the minimum requirements to achieve Materials and Resources Prerequisite, Storage and Collection of Recyclables?
Correct Answer: D
For the Materials and Resources Prerequisite, Storage and Collection of Recyclables, the project team must demonstrate that they can effectively manage and divert waste from landfills. Extending the waste stream study to a minimum of 24 hours will provide a more accurate representation of the waste generated and the recyclable streams. This is essential to identify the top five recyclable waste streams, which is a requirement for this prerequisite. References: The LEED v4 reference guide for Interior Design and Construction specifies that a waste stream audit must cover a representative time period to accurately identify the project's waste streams1. Additionally, the LEEDuser website provides guidance on how to conduct a waste stream audit and the importance of identifying the main types of recyclable waste1.