Valid OGEA-103 Dumps shared by ExamDiscuss.com for Helping Passing OGEA-103 Exam! ExamDiscuss.com now offer the newest OGEA-103 exam dumps, the ExamDiscuss.com OGEA-103 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com OGEA-103 dumps with Test Engine here:
What is an objective of the ADM Implementation Governance Phase?
Correct Answer: B
The objective of the ADM Implementation Governance Phase is to provide an architectural oversight of the implementation and to ensure conformance for the target architecture. This phase involves establishing procedures and processes to monitor and control the implementation projects and to verify that they comply with the defined architecture. Reference: The TOGAF Standard | The Open Group Website, Section 3.2.7 Phase G: Implementation Governance.