Correct Answer: C
* Definition of ADM Phase G - Implementation Governance:
* ADM Phase G, Implementation Governance, is a phase in the TOGAF Architecture Development Method (ADM) focused on ensuring that the implementation of architecture projects aligns with the target architecture.
* Objectives of Implementation Governance:
* The primary objective is to provide architectural oversight for the implementation process.
* This involves ensuring that the projects and solutions being implemented conform to the defined target architecture.
* It includes monitoring compliance, managing changes, and providing governance to support successful implementation.
* Explanation of Correct answer:
* Option A, "To ensure that the enterprise's Architecture Capability meets current requirements," is more related to the Preliminary Phase or Phase A (Architecture Vision).
* Option B, "To establish the value realization process," pertains more to Phase H (Architecture Change Management) where value realization and benefits tracking are key activities.
* Option D, "To assess the performance of the architecture and make recommendations for change," is primarily related to Phase H.
* Option C, "To ensure that implementation projects conform with the Target Architecture," is the correct objective of Phase G.
This phase is specifically designed to oversee the implementation, ensuring alignment with the target architecture and managing any deviations or changes.
References
* The Open Group. (2011). TOGAF Version 9.1. Retrieved from https://pubs.opengroup.org/architecture/togaf9-doc/arch/
* TOGAF 9 Certified Study Guide - 4th Edition.