<< Prev Question Next Question >>

Question 8/61

Scenario
Please read this scenario prior to answering the question
You are serving as the Lead Architect for the enterprise architecture team at a large multinational aerospace and defense company. The company has grown rapidly by acquisition and has inherited numerous different procurement processes and related IT systems. Several procurement processes have had problems related to the timing of purchases, which has led to excess inventory. The Vice President in charge of Supply Chain Management has made the decision to consolidate and reduce redundant procurement processes and systems. The company will move to a "Just-in-time" procurement system so as to keep inventory costs low.
TOGAF 9 is used for internal Enterprise Architecture activities. This project is using an iterative approach for executing the Architecture Development Method (ADM).
At present, there are no particularly useful architectural assets in the Architecture Repository that are related to this initiative. All assets will need to be acquired, customized, or created from scratch. The company prefers to implement commercial off the shelf package applications with little customization. The CIO, who is the project sponsor, has stated that she is not concerned about preserving the existing procurement processes or systems.
The architecture development project has completed the Preliminary Phase and has started a number of iteration cycles to develop the Architecture. As a packaged application is being considered, the next iteration will include both the Business and Application Architectures. Key stakeholder concerns that should be addressed by these architectures include:
1. What groups of people should be involved in procurement-related business processes?
2. What are the overall lifetimes of the Request for Proposal and Purchase Order business objects?
3. What non-procurement applications will need to be integrated with any new procurement applications?
Refer to the Scenario
[Note: You may need to refer to Chapter 35 of the reference text in order to answer this question.] You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support the next iteration of Architecture development.
Based on TOGAF, which of the following is the best answer?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (61q)
Question 1: Scenario: Glacier Ridge LLC Please read this scenario prior ...
Question 2: Scenario Please read this scenario prior to answering the qu...
Question 3: FreshFruit Int. is an online American grocer. The Executive ...
Question 4: Scenario: MegaMart Case Study Title (Case Study): MegaMart i...
Question 5: Scenario: Please read this scenario prior to answering the q...
Question 6: Scenario: Zephyr Enterprises Please read this scenario prior...
Question 7: Scenario Please read this scenario prior to answering the qu...
Question 8: Scenario Please read this scenario prior to answering the qu...
Question 9: Scenario: Please read this scenario prior to answering the Q...
Question 10: Scenario: Summer Seeds BV Please read this scenario prior to...
Question 11: Scenario: Please read this scenario prior to answering the Q...
Question 12: Chiamin Metals is a leading world-wide manufacturer for cont...
Question 13: Dante Manufacturing is a big supplier in the automotive indu...
Question 14: Scenario: Global Mobile 1 Please read this scenario prior to...
Question 15: Scenario: Eight Twelve Eight Twelve has retail outlets throu...
Question 16: Scenario: Zephyr Enterprises Please read this scenario prior...
Question 17: Scenario Please read this scenario prior to answering the qu...
Question 18: Worldwide Mobile is a mobile telecommunications company form...
Question 19: Scenario: Rollins Manufacturing Please read this scenario pr...
Question 20: Scenario: Please read this scenario prior to answering the Q...
Question 21: Scenario: AGEX Inc. Please read this scenario prior to answe...
Question 22: Scenario Please read this scenario prior to answering the qu...
Question 23: Scenario: St. Croix Consulting Please read this scenario pri...
Question 24: An international Insurance company has grown with little con...
Question 25: Scenario: Please read this scenario prior to answering the Q...
Question 26: Magic Wand Corporation manufactures a range of equipment use...
Question 27: Scenario: Rollins Manufacturing Please read this scenario pr...
Question 28: Scenario: Please read this scenario prior to answering the Q...
Question 29: TP Banking is a strong financial institute with a well-known...
Question 30: Scenario Please read this scenario prior to answering the qu...
Question 31: Scenario Please read this scenario prior to answering the qu...
Question 32: Scenario: Armstrong Defense Industries Please read this scen...
Question 33: Scenario Please read this scenario prior to answering the qu...
Question 34: Scenario: Please read this scenario prior to answering the Q...
Question 35: Scenario: Vittronics Ltd. Please read this scenario prior to...
Question 36: ARTI Dimensioning is a multinational that operates productio...
Question 37: Scenario: Raxlon Inc. Case Study Title (Case Study): Raxlon ...
Question 38: Please read this scenario prior to answering the question Yo...
Question 39: Scenario Please read this scenario prior to answering the qu...
Question 40: UTrack Transports is a strong UK logistics company. The head...
Question 41: Scenario: Please read this scenario prior to answering the Q...
Question 42: Scenario: Please read this scenario prior to answering the q...
Question 43: Carter Woods, a global furniture firm, wants to improve the ...
Question 44: TotalComms is a telecommunications company formed from the m...
Question 45: Scenario: Florian Flowers BV Please read this scenario prior...
Question 46: Scenario: AutoComp Corporation AutoComp Corporation produces...
Question 47: Scenario: Marona Inc. Marona Inc is a Fortune 500 Enterprise...
Question 48: Scenario: Please read this scenario prior to answering the q...
Question 49: Scenario: AGEX Inc. Please read this scenario prior to answe...
Question 50: Scenario Please read this scenario prior to answering the qu...
Question 51: Scenario: Vittronics Ltd. Please read this scenario prior to...
Question 52: MightyGears produces components for the Car industry. Driven...
Question 53: RIG Networks, a global network supplier is implementing a ma...
Question 54: Scenario: Sollace Manufacturing Please read this scenario pr...
Question 55: SureFlight Air Carrier has received approval for the acquisi...
Question 56: Scenario Please read this scenario prior to answering the qu...
Question 57: Patterns &amp; Co. is introducing a Commercial Off-the-Shelf...
Question 58: McKinley Rockets is an enterprise that employs 20,000 men an...
Question 59: Scenario: Please read this scenario prior to answering the Q...
Question 60: Scenario Please read this scenario prior to answering the qu...
Question 61: Scenario: Please read this scenario prior to answering the Q...