Question 52/100

Program Stakeholders, the Program Product Owner, Program Scrum Master, and Chief Product Owner have gathered together to create the Project Vision. They are trying to determine and document the difference between current business capabilities and the final desired set of capabilities. Which one of the following should they use to arrive at a conclusive decision?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (100q)
Question 1: The Scrum Master must ensure that a sustainable pace is main...
Question 2: All of the following statements about Risk Communications ar...
Question 3: Scrum effectively limits the risk of unknowingly doing somet...
Question 4: You are the Scrum Master on a project to develop machine par...
Question 5: Which of the following statements is NOT true of an Impedime...
Question 6: You are the Scrum Master for a team that is working on a pro...
Question 7: You are a Scrum Master on a project that is preparing to beg...
Question 8: Which of the following methods helps estimate the value prov...
Question 9: The Chief Scrum Master facilitates the Scrum of Scrums Meeti...
Question 10: Which of the following statements is NOT true of an Impedime...
Question 11: Joan is the Scrum Master for her organization and the Develo...
Question 12: Which of the following should be cross-functional?...
Question 13: At the end of each Sprint the Scrumboard is _________....
Question 14: Which of the following best defines the team velocity metric...
Question 15: What is Quality Assurance?
Question 16: Which of the following is the correct format for writing a U...
Question 17: The Chief Scrum Master plays an important role during the Re...
Question 18: The Scrum Master can help the Product Owner update business ...
Question 19: Which of the following events does NOT help the Scrum Team i...
Question 20: The Scrum Master can help the Product Owner update business ...
Question 21: What is the recommended size of a Development Team?...
Question 22: Which of the following comparisons is true about Scrum and T...
Question 23: The senior management of a multi-national company undertakes...
Question 24: Which of the following is NOT an objective of a Retrospect S...
Question 25: The Scrum Master can help the Product Owner deploy Product R...
Question 26: Collaboration is one of the Scrum principles. Which of the f...
Question 27: As a Scrum Master, you have to coordinate with the Product O...
Question 28: Scrum Masters have to solve both internal and external imped...
Question 29: What is Quality Assurance?
Question 30: As a Scrum Master, it is important that you assess skill gap...
Question 31: Which of the following comparisons is true about Scrum and T...
Question 32: Which of the following best defines the team velocity metric...
Question 33: Which of the following is NOT a Scrum Master's responsibilit...
Question 34: As a Scrum Master how will you coordinate with the Product O...
Question 35: While performing a cost-benefit analysis, the Product Owner ...
Question 36: You are the Scrum Master on a project that is reconstructing...
Question 37: A Scrum Team is estimating the prioritized User Stories. Eac...
Question 38: Emily has taken on the role of Scrum Master on a new project...
Question 39: Which of the following is NOT a ScrumMaster's responsibility...
Question 40: All of the following events and activities are examples of a...
Question 41: Which of the following is NOT a Scrum Master's responsibilit...
Question 42: You are a Scrum Master on a project creating an optical fibe...
Question 43: George is a Scrum Master on a project to develop a Course Ma...
Question 44: A Scrum Team must produce the following artifacts. Select al...
Question 45: During a Scrum of Scrums Meeting certain Question:s are answ...
Question 46: Each Scrum role has specific responsibilities in managing a ...
Question 47: Peter is a Scrum Master on a software development project fo...
Question 48: Which of the following best describes why Epics are decompos...
Question 49: Which of the following methods helps estimate the value prov...
Question 50: While assisting the Product Owner in developing a Prioritize...
Question 51: While assisting the Product Owner in developing a Prioritize...
Question 52: Program Stakeholders, the Program Product Owner, Program Scr...
Question 53: Each Scrum role has specific responsibilities in managing a ...
Question 54: Which of the following is a tool that can be used for commun...
Question 55: Which of the following is true about a Prioritized Product B...
Question 56: Van is theProduct Owner for the JK Project. He's asked you f...
Question 57: You are the Scrum Master of a project to construct an IT Tec...
Question 58: You are the Scrum Master ofthe JKM Project and your Developm...
Question 59: The Chief Scrum Master is a part of the Scrum Core Team that...
Question 60: Who among the following can directly approve changes recomme...
Question 61: As a Scrum Master you should be familiar with all roles and ...
Question 62: Which of the following are important selection criteria whil...
Question 63: Which one of the following statements about the history of S...
Question 64: Scrum Master is the 'servant leader' of Scrum Team. In this ...
Question 65: How long is a Sprint Retrospective in a one month Sprint?...
Question 66: A User Story is considered complete only when the which of t...
Question 67: Marty is coaching the Development Team on being completely d...
Question 68: Marty is coaching theDevelopment Team on being completely do...
Question 69: How long is a Sprint Retrospective in a one month Sprint?...
Question 70: During the Form Scrum Team process, the Scrum Master must co...
Question 71: Which of the following about User Story Acceptance Criteria ...
Question 72: The table given below presents some Scrum roles that play an...
Question 73: The table given below presents some Scrum roles that play an...
Question 74: The Scrum Master can help the Product Owner deploy Product R...
Question 75: To ensure that there is no gap between the customer's expect...
Question 76: You are a Scrum Master on a project creating an optical fibe...
Question 77: Which of the following is NOT an objective of a Retrospect S...
Question 78: Between traditional Project Management and Scrum, difference...
Question 79: During a Scrum of Scrums, each Scrum Team representative pro...
Question 80: Lynn is the Scrum Master for her organization and she's work...
Question 81: Scrum can easily be scaled for effective use in large projec...
Question 82: You are working in a $50 million project to remove weeds fro...
Question 83: A User Story is considered complete only when the which ofth...
Question 84: Which of the following statements about Release Planning Ses...
Question 85: During a Scrum of Scrums, each Scrum Team representative pro...
Question 86: To enable collaboration, the Product Owner, the Scrum Master...
Question 87: Impediments are a part of any project. Which of the followin...
Question 88: Which one of the following is NOT a type of identified depen...
Question 89: You are a Scrum Master on a project that is preparing to beg...
Question 90: George is a Scrum Master on a project to develop a Course Ma...
Question 91: Beth is a Scrum Master over a newly formed team. What can Be...
Question 92: The Scrum Master can help the Product Owner deploy Product R...
Question 93: Impediments are a part of any project. Which of the followin...
Question 94: Which of the following methods helps estimate the value prov...
Question 95: Which of the following is a process in the initiate phase of...
Question 96: Which of the following is NOT an objective of a Retrospect S...
Question 97: Which of the following is NOT an objective of a Retrospect S...
Question 98: Which of the following is true about a Prioritized Product B...
Question 99: A large software company has 8 Scrum teams with each team ha...
Question 100: To enable the Product Owner to successfully deploy the produ...