The Definition of Done is used to: (choose the best three answers)
Correct Answer: A,C,D
* A. Increase transparency: The Definition of Done (DoD) creates transparency by providing everyone a shared understanding of what work was completed and what standards were met as part of the Increment1. * C. Create a shared understanding of when work is complete: The DoD is a shared understanding among the team members of when a product increment is ready for release2. * D. Describe the work that must be done before the Sprint can be declared complete: The DoD includes all of the characteristics and standards an Increment needs to meet in order to be released1. Once the Definition of Done is met, the Increment is Done and can be delivered1.