When the Developers determine that they will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer)
Correct Answer: D
The correct answer isD. During the Sprint, if the work turns out to be different from what the Developers expected, the Developers collaborate with the Product Owner to negotiate the scope of the Sprint Backlog within the Sprint without affecting the Sprint Goal. This means the Product Owner and Developers are the key people involved when reviewing and adjusting the selected Sprint work. Why the other options are incorrect: A). The Product Owner and all stakeholders- stakeholders are not required for this adjustment. B). The Scrum Master and the Developers- the Scrum Master may help if needed, but the Product Owner is the required partner for scope negotiation. C). The Scrum Master, project manager and the Developers- Scrum does not define a project manager role here, and this is not the required group. The Scrum Guide supports this by stating that as more is learned, the Developers and the Product Owner may renegotiate the scope of the Sprint Backlog.