During the Sprint Retrospective a Scrum Team has identified several high priority process improvements. Which of the following statements is most accurate? (choose the best answer)
Correct Answer: A
The Scrum Guide states that "By the end of the Sprint Retrospective, the Scrum Team should have identified improvements that it will implement in the next Sprint. Implementing these improvements in the next Sprint is the adaptation to the inspection of the Scrum Team itself."1 This means that the Scrum Team may add the high priority process improvements to the Sprint Backlog for the next Sprint, as part of their plan to deliver the Increment and achieve the Sprint Goal. The Sprint Backlog is owned and managed by the Developers, who can update it throughout the Sprint as more is learned.1 References: * 1: The Scrum Guide2, page 16 * 2: The Scrum Guide