What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint? (choose the best answer)
Correct Answer: B
Explanation the Product Owner is responsible for refining the Product Backlog, which is an ongoing activity that can occur at any time, including between Sprints. The other options are not typical activities for the Product Owner between Sprints, as the next Sprint starts immediately after the current Sprint1, the project plan is replaced by the Product Backlog2, and the Quality Assurance is done by the Developers of the Scrum Team within the Sprint1. 1: The Scrum Guide | Scrum.org 2: What is a Product Backlog? | Scrum.org
Recent Comments (The most recent comments are at the top.)
Peter Rohner - Feb 07, 2024
Hi there, I found an error in the response of your PSPO I exam questions: Home / Scrum / Professional Scrum Product Owner I / Scrum.PSPO-I.v2024-01-22.q54 / Question 29
Q: What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint? (choose the best answer)
Your incorrect answer: B. Refine the Product Backlog. Correct answer should be: A. There are no such activities. The next Sprint starts immediately after the current Sprint.
Refinement of the Product Backlog can be down when ever the Scrum Team has time to do in durring the sprint.
Recent Comments (The most recent comments are at the top.)
Hi there, I found an error in the response of your PSPO I exam questions:
Home / Scrum / Professional Scrum Product Owner I / Scrum.PSPO-I.v2024-01-22.q54 / Question 29
Q: What activities would a Product Owner typically undertake in the period between the end of the current Sprint and the start of the next Sprint?
(choose the best answer)
Your incorrect answer: B. Refine the Product Backlog.
Correct answer should be: A. There are no such activities. The next Sprint starts immediately after the current Sprint.
Refinement of the Product Backlog can be down when ever the Scrum Team has time to do in durring the sprint.
You will also find the same question at Scrum.org Open Assessments at:
https://www.scrum.org/open-assessments/product-owner-open
If you have any questions feel free to contact me.
Best regards