B, C, E is right
I can't entirely agree with the given answers (ADE)
A - what does the definition of "Done" has to do with the time-boxing of each Scrum event???
B - "Done" helps Developers to decide how many items to pick for Sprint
C - Definition of "Done" increases transparency
D - "the Sprint is allowed to end" - Sprint is time-boxed, and will end even if the work is not done
E - correct
C, D, E.
The Definition of Done creates transparency by providing everyone a shared understanding of what
work was completed as part of the Increment