The answer should be C: Teach them that it is their responsibility to work with the other teams to create an Integrated Increment.
Reference: https://www.scrum.org/forum/scrum-forum/6289/questions
Where multiple teams are involved in creating an Increment the responsibility for integrating work products is commonly shared. The teams are expected to self-organize, and to ensure that an integrated and potentially releasable Increment is planned and delivered. The Scrum Master should coach them to do this as effectively as possible. This is therefore a very good answer.