Valid PSK-I Dumps shared by ExamDiscuss.com for Helping Passing PSK-I Exam! ExamDiscuss.com now offer the newest PSK-I exam dumps, the ExamDiscuss.com PSK-I exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PSK-I dumps with Test Engine here:
What does it mean when a Scrum Team chooses to communicate an 85% 5-day service level expectation (SLE)?
Correct Answer: C
An SLE of 85% for 5 days signifies that the team anticipates they will complete items within 5 days, 85% of the time. This helps set clear expectations with stakeholders, ensuring transparency around potential delivery timelines. The SLE is based on historical data and provides a probability-based forecast, rather than a commitment. References: The Kanban Guide for Scrum Teams.