You manage a product development organization. You are looking at the progress reports from a number of Scrum Teams in your organization, when you notice that while most teams have a velocity of 35-40 story points per Sprint, one team consistently delivers only 15-20 per Sprint. Is this cause for concern? (choose the best answer)
Correct Answer: B
Velocity is a measure of how much work is completed by a team in a Sprint but does not directly indicate the value being delivered. It is not appropriate to compare velocities across different teams because each team may estimate story points differently. The focus should be on whether the team is delivering valuable increments of work, not their velocity.