Universal Containers is currently using the 'Resource Efficiency' feature in Field Service. The estimated duration for a replacement job is one hour, and the efficiency setup is as follows: X is an expert, 'Efficiency' = 2.00 Y is a technician, 'Efficiency' = 1.00 Z is a junior technician, 'Efficiency' = 0.50 What will be the calculated duration of the Service Appointment when assigned to the different Service Resources?
Correct Answer: B
Resource Efficiency is a multiplier that adjusts how long a particular resource needs to complete a job: duration = base duration / efficiency. An expert (efficiency > 1) takes less time, and a junior (efficiency < 1) takes more. * Option B is correct. Applying the formula to a base 60-minute job: X = 60 / 2.00 = 30 minutes, Y = 60 / 1.00 = 60 minutes, Z = 60 / 0.50 = 120 minutes. * Option A is incorrect because 90 minutes for Z does not match the formula; 60 / 0.5 = 120, not 90. * Option C is incorrect because it inverts the relationship - an expert takes less time, not more. * Option D is incorrect because it ignores efficiency entirely.