Valid E_ACTAI_2403 Dumps shared by ExamDiscuss.com for Helping Passing E_ACTAI_2403 Exam! ExamDiscuss.com now offer the newest E_ACTAI_2403 exam dumps, the ExamDiscuss.com E_ACTAI_2403 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com E_ACTAI_2403 dumps with Test Engine here:
What are key goals of the burndown chart? Note: There are 2 correct ans-wers to this que-stion.
Correct Answer: C,D
Key goals of the burndown chart in Agile project delivery include: * C. Visualization of the size of the backlog consumed so far: The burndown chart provides a visual representation of work completed over time against the total work scope, helping teams track progress and pace. * D. Determination of the planned go-live date based on current velocity: By analyzing the rate at which the team is completing work, project managers can forecast when the project is likely to be completed, which aids in planning for the go-live date. Options A (Determination of the overall availability of the team for the future sprints) and B (Assignment of backlog items to future sprint up to completion of the release) are not direct goals of the burndown chart; these aspects are more related to sprint planning and capacity management.References: * Agile project management tools and their uses * Effective use of burndown charts in project management Agile Project Delivery