Valid C_TS452_2022 Dumps shared by ExamDiscuss.com for Helping Passing C_TS452_2022 Exam! ExamDiscuss.com now offer the newest C_TS452_2022 exam dumps, the ExamDiscuss.com C_TS452_2022 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS452_2022 dumps with Test Engine here:
Your MRP run detects a shortage of 2000 pieces for a material with an active quota arrangement. Each of your two suppliers can only supply 1000 pieces at once. What must you maintain to have MRP generate a procurement proposal for 1000 pieces for each supplier? Note: There are 2 correct answers to this question.
Correct Answer: A,C
Explanation To have MRP generate a procurement proposal for 1000 pieces for each supplier, you must maintain the following: Set a maximum lot size in the quota arrangement item and activate the lx checkbox, which means that MRP will split the total requirement quantity according to the quota allocation and create one procurement proposal per quota arrangement item. Set a maximum quota quantity in the quota arrangement item for each supplier, which limits the total quantity that can be procured from each supplier within a validity period. References: SAP S/4HANA Sourcing and Procurement | SAP Learning, Course S4525, Unit 1, Lesson 1.