Valid C_TS422_2023 Dumps shared by ExamDiscuss.com for Helping Passing C_TS422_2023 Exam! ExamDiscuss.com now offer the newest C_TS422_2023 exam dumps, the ExamDiscuss.com C_TS422_2023 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS422_2023 dumps with Test Engine here:
You want to set up a maketoorder planning scenario for a finished product. The bill of material contains two components: one should be procured for eac sales order individually the other should be procured jointly for all independent requirements. Forecasting for the finished product is NOT possible. Which settings do you make to achieve this?