Question 36/39

Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20.
The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day.
What do you recommend to set up the requirement date for the component ?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (39q)
Question 1: You have assigned a material to a network activity and want ...
Question 2: Project Structure You plan double the work on each internal ...
Question 3: What are valid procurement types for stock items? Note: Ther...
Question 4: Cost &amp; Budget. A customer wants to allocate overhead rat...
Question 5: Where can you assign the use status profile for WBS elements...
Question 6: Resources Which of the following transactions can you use to...
Question 7: Your customer has created networks with internal activities ...
Question 8: You are using networks and external activities in your proje...
Question 9: Which orders or documents can be displayed in Project-Orient...
Question 10: Material You want to create purchase requisition for the mat...
Question 11: What are the prerequisites for resource-related billing? Not...
Question 12: What business transactions can be used with Project-Oriented...
Question 13: You want to use subnetworks during the project. Which of the...
Question 14: An external component is assigned to a network activity. The...
Question 15: Which statements describe planned and actual revenue for WBS...
Question 16: Material How can the system activate requirements (such as r...
Question 17: In your project. You work with a network and external activi...
Question 18: How can you search in the structure overview based on the us...
Question 19: You want to use billing for a customer project. Which custom...
Question 20: What are the prerequisites for delivering materials from the...
Question 21: Project structure You want use a template to create a new pr...
Question 22: Resources How can you define external task in your project. ...
Question 23: You are using budgeting and active availability control. How...
Question 24: How can you confirm the working hours of different work cent...
Question 25: Where do you control whether a project stock is managed as v...
Question 26: Which of the following apply to dynamic item processor (DIP)...
Question 27: Which of the following actions can transfer actual costs for...
Question 28: The__________________that you specify when you create a proj...
Question 29: Cost &amp; Budget You are using network and internal activit...
Question 30: A service company uses project management and they complain ...
Question 31: How are earliest dates and latest dates of activities schedu...
Question 32: Which objects do you have to maintain to enable automatic as...
Question 33: Which planning method can prevent further rescheduling of ac...
Question 34: To which object can you assign a factory calendar?...
Question 35: Revenues &amp; Payment Your customer wants to plans and post...
Question 36: Your customer's projects are subject to recurring changes of...
Question 37: Which of the following statements apply to project versions?...
Question 38: Resources How are capacity requirements determined?...
Question 39: Budgeting is implemented for projects. The budget has been a...