Valid C_TS412_1909 Dumps shared by ExamDiscuss.com for Helping Passing C_TS412_1909 Exam! ExamDiscuss.com now offer the newest C_TS412_1909 exam dumps, the ExamDiscuss.com C_TS412_1909 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS412_1909 dumps with Test Engine here:

Access C_TS412_1909 Dumps Premium Version
(112 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 18/28

In your project, you work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

Recent Comments (The most recent comments are at the top.)

Alan Cheng - May 10, 2022

The correct answer should be D. Please check

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (28q)
Question 1: What are some of the advantages of using project simulations...
Question 2: What functionality can you perform with activity elements?...
Question 3: Your customer's projects are subject to recurring changes of...
Question 4: Where do you control whether a project stock is managed as v...
Question 5: To which object can you assign a factory calendar?...
Question 6: What are valid procurement types for stock items? Note: Ther...
Question 7: Float time is calculated during scheduling. Which of the fol...
Question 8: What are the prerequisites for resource-related billing? Not...
Question 9: The basic dates of subordinate WBS elements should be extrap...
Question 10: Which objects can be used to specify settlement rules? Note:...
Question 11: You plan an activity that starts on February 1 and finishes ...
Question 12: A customer project must be finished at a given due date. The...
Question 13: A service company uses project management and they complain ...
Question 14: Which of the following statements apply to project versions?...
Question 15: Where do you control whether a project stock is managed as v...
Question 16: Where can you define a network as "header-account-assigned" ...
Question 17: Which object is used to allocate the costs from a claim to t...
1 commentQuestion 18: In your project, you work with a network and external activi...
Question 19: Where do you maintain the length of the project ID?...
Question 20: A customer needs to analyse the capacity requirements of the...
Question 21: You want to create a reservation for a material component as...
Question 22: Which planning method can prevent further rescheduling of ac...
Question 23: You want to allocate overhead rates to a WBS element. What m...
Question 24: You are working with predefined project coding masks to crea...
Question 25: You used hierarchical revenue planning to plan revenues for ...
Question 26: The system status of a WBS element is created (CRTD). Which ...
Question 27: You are using WBS elements and activities are NOT assigned. ...
Question 28: You used reductions to reduce the scheduled duration of all ...