Valid C_TS410_2022 Dumps shared by ExamDiscuss.com for Helping Passing C_TS410_2022 Exam! ExamDiscuss.com now offer the newest C_TS410_2022 exam dumps, the ExamDiscuss.com C_TS410_2022 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TS410_2022 dumps with Test Engine here:
When running MRP, what setting in the material master determines if a material will be procured or produced?
Correct Answer: A
In the material master, the Procurement Type (A) setting determines whether a material will be procured externally, produced in-house, or both. This setting is crucial for Material Requirements Planning (MRP), as it guides the MRP system on how to replenish thematerial - by generating purchase requisitions for external procurement or planned orders for in-house production.References= SAP Material Management (MM) and Production Planning (PP) documentation.