Valid C_TPLM22_67 Dumps shared by ExamDiscuss.com for Helping Passing C_TPLM22_67 Exam! ExamDiscuss.com now offer the newest C_TPLM22_67 exam dumps, the ExamDiscuss.com C_TPLM22_67 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_TPLM22_67 dumps with Test Engine here:
Assume a scenario where in, during the planning phase you entered basic dates for WBS elements, for instance by creating graphical time bars in the project planning board and as a result in the execution phase you have an option to set the actual dates in the sameway in the project planning board. What is the status that must be set before you can enter actual start and actual end dates? There are 2 correct answers to this question. Response: