After you completed the Explore Phase Quality Gate you notices that the Fit to Standard workshops have been carried out without the input of the finance experts of the Australian office of the customer. The Australian office is scheduled to go live in an later implementation phase.
What should you do?
Note: There are 2 correct answers to this question.