Valid C_S4CCO_2506 Dumps shared by ExamDiscuss.com for Helping Passing C_S4CCO_2506 Exam! ExamDiscuss.com now offer the newest C_S4CCO_2506 exam dumps, the ExamDiscuss.com C_S4CCO_2506 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_S4CCO_2506 dumps with Test Engine here:
You have just performed the final goods receipt for a production order.What are the consequences in event-based ? Note: There are 3 Correct Answe rs to this questio n.
Correct Answer: A,B,D
Solution: The correct consequences, according to learning.sap.com, when you perform the final goods receipt for a production order in event-based are: ✅ Correct Answe rs A . Settlement performed * The final goods receipt triggers an event-based settlement, which clears both the order balance and any remaining WIP. SAP Help Portal+8SAP Learning+8SAP Learning+8 B . Variances posted * As part of the automatic settlement, production variances are calculated and posted. SAP Learning+5SAP Learning+5SAP Learning+5 D . Target costs updated * The system recalculates target costs based on the received quantities and adjusts the production order accordingly. SAP Help Portal+9SAP Learning+9SAP Learning+9 ❌ Not Correct * C. Work in progress (WIP) debited - No; WIP is cleared (credited) with the final goods receipt, not increased. * E. Actual costs increased - Incorrect; actual costs are decreased when the order is credited during settlement. 📝 Final Selection: * A. Settlement performed * B. Variances posted * D. Target costs updated System Landscapes and Identity Access Management