Valid C_BYD15_1908 Dumps shared by ExamDiscuss.com for Helping Passing C_BYD15_1908 Exam! ExamDiscuss.com now offer the newest C_BYD15_1908 exam dumps, the ExamDiscuss.com C_BYD15_1908 exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com C_BYD15_1908 dumps with Test Engine here:
You change an active project baseline and save it. Then, the system creates a new baseline. What are the statuses of the previous baseline and new baseline?
Correct Answer: A
The correct answer is A. Previous baseline: "active with pending changes" and New baseline: "in planning". When you change an active project baseline and save it, the system creates a new baseline with the status of "in planning". Meanwhile, the previous baseline is set to "active with pending changes" to indicate that changes were made to the baseline but they have not yet been incorporated into the project.