Valid PRINCE2-Foundation Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Foundation Exam! ExamDiscuss.com now offer the newest PRINCE2-Foundation exam dumps, the ExamDiscuss.com PRINCE2-Foundation exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Foundation dumps with Test Engine here:

Access PRINCE2-Foundation Dumps Premium Version
(474 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 127/130

Identify the missing word in the following sentence.
A project's [ ? ] are the measurable improvements resulting from the outcomes achieved through the use of the project's outputs.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (130q)
Question 1: Which is NOT one of the PRINCE2 integrated elements?...
Question 2: Which is a purpose of the Initiating a Project process?...
Question 3: Which characteristic of a project reflects that there are di...
Question 4: Identify the missing word in the following sentence. The PRI...
Question 5: Which is NOT represented by one of the three primary categor...
Question 6: Which is one of the three levels of plan in PRINCE2?...
Question 7: When is the 'managing a stage boundary' process used?...
Question 8: Which process provides information for the project board to ...
Question 9: Which statement about time-driven controls is CORRECT?...
Question 10: Which two roles are linked by the Managing Product Delivery ...
Question 11: Which is an objective of the 'managing a product delivery' p...
Question 12: Which is an objective of the Managing Product Delivery proce...
Question 13: Which is a key decision made during the 'directing a project...
Question 14: Which aspect of project performance must be managed to ensur...
Question 15: What process provides information on a team's work to the pr...
Question 16: What is a supplier of a PRINCE2 project responsible for?...
Question 17: Within which integrated element does PRINCE2 set minimum req...
1 commentQuestion 18: Which is a minimum requirement for applying the business cas...
Question 19: Which are objectives of the 'managing a stage boundary' proc...
Question 20: What is documented in the project plan to support the 'manag...
Question 21: Which is a minimum requirement for applying the quality them...
Question 22: Which is an objective of the 'controlling a stage' process?...
Question 23: Which is a responsibility of the project board?...
1 commentQuestion 24: Which is the first task of PRINCE2's recommended approach to...
Question 25: Which is a purpose of the 'directing a project' process?...
Question 26: Why is a Project Brief produced?...
Question 27: Why does the project board review the PID during an end stag...
Question 28: Which is a minimum requirement for applying the organization...
Question 29: Which is an objective of the 'initiating a project' process?...
Question 30: In a commercial environment, which process links the team ma...
Question 31: Which is NOT considered when defining risk tolerance?...
Question 32: Which process is used by the project board to respond to on ...
Question 33: Which is a recommended quality review team role?...
Question 34: Which is a purpose of a Project Product Description?...
Question 35: Which is a purpose of the Starting up a Project process?...
Question 36: Which theme establishes the mechanisms to control against ba...
Question 37: Which is NOT a purpose of the Organization theme?...
Question 38: How does PRINCE2 ensure that the specific management needs o...
Question 39: Which is a purpose of a project brief?...
Question 40: To meet the minimum requirements for applying the progress t...
Question 41: Which is assumed to be a customer's responsibility in the PR...
Question 42: What is a goal of the 'implement' step within the recommende...
Question 43: Which product identifies the management stages and timescale...
Question 44: Which is a purpose of the Controlling a Stage process?...
Question 45: Which role is responsible for appointing the senior user in ...
Question 46: What is an advantage of applying the 'learn from experience'...
Question 47: In what process is the authorization to deliver the project'...
Question 48: Which is shown in a product breakdown structure?...
Question 49: Which is a responsibility of a risk owner?...
Question 50: Why is the Initiating a Project process used?...
Question 51: Which is the purpose of the Change theme?...
Question 52: What theme estimates the cost of delivering the project?...
Question 53: Which is NOT included in the PRINCE2 definition of a project...
Question 54: Which is a purpose of the Managing Product Delivery process?...
Question 55: Which is a task of product-based planning?...
Question 56: Which is a purpose of the quality theme?...
Question 57: What should the 'managing product delivery' process ensure? ...
Question 58: Which risk response is applied on a pain/gain basis?...
Question 59: Which is a typical core activity within configuration manage...
Question 60: Why is it necessary to apply the 'defined roles and responsi...
Question 61: Where can people who join a project after initiation quickly...
Question 62: Which process provides information for the project board to ...
Question 63: Which of the following statements about customer's quality e...
Question 64: Which is a purpose of the 'directing a project' process?...
Question 65: Which are purposes of the 'directing a project' process? 1. ...
Question 66: Which is a benefit of applying the 'tailor to suit the proje...
Question 67: Identify the missing words in the following sentence. When p...
Question 68: How should the "managing a stage boundary' process be used t...
Question 69: Which is a minimum requirement for applying the quality them...
Question 70: Which is a difference between management and technical stage...
Question 71: Identify the missing word(s) in the following sentence. PRIN...
Question 72: Which role is responsible for ensuring the project is justif...
Question 73: Which control must be used as a minimum requirement for appl...
Question 74: Which characteristic distinguishes a project from regular bu...
Question 75: Which of the following statements about the Closing a Projec...
Question 76: During the Managing a Stage Boundary process what product is...
Question 77: Which is a minimum requirement for applying the change theme...
Question 78: Whose approval is needed to replace a Stage Plan with an Exc...
Question 79: When should the Project Board refer to corporate or programm...
Question 80: Identify the missing word in the following sentence. [ ? ] i...
Question 81: According to the 'defined roles and responsibilities' princi...
Question 82: What should the benefits management approach define?...
Question 83: Which are purposes of the quality theme? 1. To implement con...
Question 84: Which is the base product against which the Project Board ca...
Question 85: Why is it crucial that the Project Product Description clear...
Question 86: According to PRINCE2, which characteristic is necessary for ...
Question 87: Identify the missing words in the following sentence. The 's...
Question 88: Which is the Issue Register NOT used for?...
Question 89: Which is a benefit of using PRINCE2?...
Question 90: Identify the missing word(s) in the following sentence. Duri...
Question 91: Which level of management uses the mechanisms established by...
Question 92: Which are characteristics of stakeholders? 1. They are often...
Question 93: During the 'initiating a project' process, who specifies the...
Question 94: Which is part of quality control?...
Question 95: What should be considered when defining the number of manage...
Question 96: Identify the missing words in the following sentence. PRINCE...
Question 97: Which is a factor when deciding the duration of a management...
Question 98: Which statement about the quality review technique is FALSE?...
1 commentQuestion 99: Which product is created in the 'starting up a project' proc...
Question 100: Which describes a risk event?
Question 101: Which is NOT a purpose of the Initiating a Project process?...
Question 102: Which is a minimum requirement for applying the plans theme?...
Question 103: Identify the missing words in the following sentence. A purp...
Question 104: Which product identifies how often stakeholders require info...
Question 105: Which is a purpose of the quality theme?...
Question 106: How does the project plan help to support the 'manage by sta...
Question 107: What is performed as part of the recommended risk management...
Question 108: Which describes a time-driven control?...
Question 109: Which is a purpose of the 'managing a stage boundary' proces...
Question 110: Who represents the three project interests on a project?...
1 commentQuestion 111: Which is a purpose of the 'initiating a project' process?...
Question 112: What is an advantage of dividing the project into stages?...
Question 113: Which plan provides the Business Case with costs during the ...
Question 114: Why can PRINCE2 be applied to any type of project?...
Question 115: How many roles make up the Project Board?...
Question 116: What product defines the reporting requirements between the ...
Question 117: Which should be provided by corporate or programme managemen...
Question 118: Which describes an off-specification?...
Question 119: Who should act as the communication channel between a projec...
Question 120: Which is an objective of the Starting up a Project process?...
Question 121: Which is a purpose of the Risk theme?...
Question 122: Where should a team manager look for information about the q...
Question 123: Which is part of quality control?...
Question 124: Which process ensures focus on the delivery of a stage's pro...
Question 125: Which statement describes the 'Implement' step within the re...
Question 126: Identify the missing words in the following sentence. The ro...
Question 127: Identify the missing word in the following sentence. A proje...
Question 128: Which is NOT a purpose of a Benefits Review Plan?...
Question 129: What takes place during the Closing a Project process?...
Question 130: A product can NOT be supplied to meet all of the requirement...