Question 78/170

Which of the following are uses of the Risk Register during the Controlling a Stage process?
1.Obtain details on risks to include in a Highlight Report
2.Obtain details of risks that may affect the Stage Plan for the next stage
3.Capture uncertainties identified when authorizing a Work Package
4.Obtain details of any potential impacts that may affect the Business Case while reviewing the stage status

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (170q)
Question 1: Which theme has a purpose of providing the mechanisms to for...
Question 2: Which role is the key decision-maker on the project manageme...
Question 3: Which is a purpose of a Configuration Management Strategy?...
Question 4: In which process would a concern about the amount of stage t...
Question 5: If, for whatever reason, the business justification disappea...
Question 6: Which of the following are product-based planning tasks? 1. ...
Question 7: In what product would a product's quality tolerance be defin...
Question 8: Identify the missing word(s) from the following sentence. A ...
Question 9: Which process would check and accept Work Packages?...
Question 10: Which PRINCE2 principle supports planning only to a level of...
Question 11: Identify the missing word in the following sentence... A Pro...
Question 12: Which of the following describes the situation when an Issue...
Question 13: Once the project has been authorized, within which process a...
Question 14: When it is forecast that one or more tolerances are to be ex...
Question 15: Why does PRINCE2 recommend having three levels of plan?...
Question 16: Identify the missing word(s) in the following sentence... Qu...
Question 17: What process covers the acceptance and execution of project ...
Question 18: Which level of management has control over a Work Package, a...
Question 19: Which is an objective of the quality review technique?...
Question 20: What is NOT identified when creating a product breakdown str...
Question 21: Which product identifies the source products from which a pr...
Question 22: Which of the following are valid risk responses for threats?...
1 commentQuestion 23: Which describes risk appetite?
Question 24: Who are allowed to raise issues?...
Question 25: Which of the following is a request for change?...
Question 26: What characteristic relates to a project having a defined st...
Question 27: What process ensures that plans for achieving the expected b...
Question 28: The Managing Product Delivery process views the project from...
Question 29: Which theme includes the estimating of the effort required t...
Question 30: Which role is part of the project management team?...
Question 31: Which of the following is NOT a typical activity of a config...
Question 32: Which product establishes the baseline against which the pro...
Question 33: Identify the missing word(s) in the following sentence... Th...
Question 34: Which of the following would be carried out as part of a pos...
Question 35: What is NOT a purpose of the End Stage Report?...
Question 36: Are the following statements regarding technical stages true...
Question 37: In respect of the project's organization structure, one of t...
Question 38: Which process provides an opportunity to ensure that all una...
Question 39: Whose responsibility is it to assure the project's stakehold...
Question 40: If a Work Package is forecast to exceed its tolerances, how ...
Question 41: Which statement describes risk cause?...
Question 42: What environment does PRINCE2 assume?...
Question 43: Are the following statements regarding the Communication Man...
Question 44: What is the trigger for the Starting up a Project process?...
Question 45: Which product is the Executive specifically responsible for ...
Question 46: For whom does the Senior User make decisions on behalf of?...
Question 47: Which level of management in the project management team has...
Question 48: Which of the following would contain the business option of ...
Question 49: According to PRINCE2, as well as holding informal problems/c...
Question 50: Identify the missing words in the following sentence. The Pr...
Question 51: Which of the following statements is TRUE?...
Question 52: The PRINCE2 principle 'focus on products' states that a succ...
Question 53: What is a purpose of the Risk Management Strategy?...
Question 54: Which is NOT an event-driven control?...
Question 55: Which of the following shows the scope of a plan?...
Question 56: Which role does PRINCE2 state would contribute expertise in ...
Question 57: Which of the following describes risk proximity?...
Question 58: Which process has a specific objective to ensure there is bu...
Question 59: What is a purpose of a Daily Log?...
Question 60: Which of the following steps looks at the aggregated net eff...
Question 61: What is produced by the Project Manager to define and keep c...
Question 62: Select the missing words from the following sentence... The ...
Question 63: When authorizing a stage, in which product would the Project...
Question 64: What principle is supported by the Project Product Descripti...
Question 65: Which of the following is a specific quality review role res...
Question 66: Which of the following is NOT within the authority of the Pr...
Question 67: What role is responsible for creating a Team Plan in the Man...
Question 68: Who are allowed to raise an issue?...
Question 69: Which product is used to inform the Project Board of a forec...
Question 70: The creation of an Exception Plan often follows which situat...
Question 71: Are the right people being involved in writing Product Descr...
Question 72: When producing an Exception Plan for a stage, why would the ...
Question 73: What is a purpose of the Communication Management Strategy?...
Question 74: Which is NOT an objective of the Directing a Project process...
Question 75: Which role has a specific responsibility for referring to th...
Question 76: The Controlling a Stage process is used for which of the fol...
Question 77: Which process can trigger a premature close of the project?...
Question 78: Which of the following are uses of the Risk Register during ...
Question 79: Which of the following are a purpose of an Issue Report? 1.D...
Question 80: Which of the following is a specific objective of the Managi...
1 commentQuestion 81: Which step in the issue and change control procedure would b...
Question 82: Identify the missing word from the following sentence... PRI...
Question 83: Within the PRINCE2 customer/supplier environment, what is a ...
Question 84: What is NOT an objective of the Directing a Project process?...
Question 85: Which product produced at project closure would document any...
Question 86: Identify the missing words in the following sentence... A PR...
Question 87: Which is NOT a purpose of the Plans theme?...
Question 88: Please refer to section 8.2.1 in the PRINCE2 Manual. (The an...
Question 89: Which of the following steps would involve the actioning of ...
Question 90: Which role has a specific responsibility for identifying and...
Question 91: Which of the following products is used after the Starting U...
Question 92: Which PRINCE2 role has a specific responsibility for referri...
Question 93: Which of the following is a quality review team role?...
Question 94: Which of the following are a purpose of the Benefits Review ...
Question 95: What is a purpose of the Initiating a Project process?...
Question 96: Which product is continuously maintained in order to inform ...
Question 97: Identify the missing words in the following sentence.... The...
Question 98: Which is a definition of a risk cause?...
Question 99: Which of the following is FALSE regarding an Exception Repor...
Question 100: Which of the following is FALSE?...
Question 101: Which is a purpose of the Business Case theme?...
Question 102: Which of the following are benefits of using PRINCE2? 1.Prov...
Question 103: Where would a Team Manager find information regarding the sp...
1 commentQuestion 104: In what process are the project's risk management techniques...
Question 105: What is risk appetite?
Question 106: Which of the following is NOT a PRINCE2 Principle?...
Question 107: Which of the following steps would involve the actioning of ...
Question 108: Which is an objective of the Managing a Stage Boundary proce...
Question 109: What process enables an organization to understand the work ...
Question 110: Identify the missing words in the following sentence... PRIN...
Question 111: Which product would be updated to show that a decision has b...
Question 112: Which product would contain information on project and stage...
Question 113: In which situation might the Controlling a Stage process be ...
Question 114: Which of the following documents the quality techniques, sta...
Question 115: Which of the following would be defined within the Project B...
Question 116: The creation of an Exception Plan often follows which of the...
Question 117: Which is a characteristic of a project?...
Question 118: Which role has a specific responsibility for planning, monit...
Question 119: Which of the following does PRINCE2 recognize as being proje...
Question 120: Which is a specific responsibility of Project Assurance?...
Question 121: Which product would be updated with the planned quality mana...
Question 122: Which process ensures that provision has been made to addres...
Question 123: Which process would ensure that there is continued business ...
Question 124: Which of the following is within the context of the Closing ...
Question 125: Identify the missing word(s) in the following sentence... Th...
Question 126: Which is the base product against which the Project Board an...
Question 127: What product is reviewed by the Project Manager as part of p...
Question 128: Which is NOT established as part of the Starting Up a Projec...
Question 129: A pre-requisite of effective issue and change control is the...
Question 130: Which of the following is a PRINCE2 principle?...
Question 131: When is the Risk Management Strategy produced?...
Question 132: What is the goal of the 'Identify context' step within the r...
Question 133: Which of the following risk responses can be used to seize a...
Question 134: How does the Progress theme assist the Project Board to asse...
Question 135: The reviewer(s) and approver(s) of a particular product are ...
Question 136: Identify the missing word(s) in the following sentence... PR...
Question 137: If any type of issue or risk (or aggregation of them) cannot...
Question 138: The Project Board needs to assess project viability at certa...
Question 139: Whose responsibility is it to ensure that the project is foc...
Question 140: Which of the following are correct regarding the definition ...
Question 141: Which product is used to record information regarding any is...
Question 142: Which of the following is a typical activity of a configurat...
Question 143: Which of the following statements are correct regarding the ...
Question 144: What is a purpose of the Business Case theme?...
Question 145: In PRINCE2, the information regarding the business justifica...
Question 146: What is defined within the Organization theme?...
Question 147: What's the purpose of the 'Plan' step within the risk manage...
Question 148: Which of the following information does a Product Descriptio...
Question 149: Identify the missing words in the following sentence... A Pr...
Question 150: What is a purpose of a Lessons Log?...
Question 151: In which product are acceptance criteria documented?...
Question 152: Identify the missing words in the following sentence... A PR...
Question 153: Who determines the use of a change authority and change budg...
Question 154: Which of the following steps looks at the aggregated net eff...
Question 155: The outputs from a PRINCE2 project are considered to be what...
Question 156: Which of the following is a Project Board control?...
Question 157: Which is an objective of the Closing a Project process?...
Question 158: Which product would be updated to show that a decision has b...
Question 159: Which of the following, produced in the Starting Up a Projec...
Question 160: Who is responsible for providing the project mandate?...
Question 161: Which of the following would be done during the initiation s...
Question 162: Which project management team role has a specific responsibi...
Question 163: What is a responsibility of the business representative on t...
Question 164: Which of the following PRINCE2 elements are described as bei...
Question 165: Which is a purpose of a Configuration Item Record?...
Question 166: Which is NOT a factor to consider when defining management s...
Question 167: What name is given to the permissible deviation allowed abov...
Question 168: A pre-requisite of effective issue and change control is the...
Question 169: According to PRINCE2, which of the following roles can the P...
Question 170: Which role is accountable to corporate or programme manageme...