<< Prev Question Next Question >>

Question 43/105

Which is a purpose of the Risk Register?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (105q)
Question 1: During the Managing a Stage Boundary process what product is...
Question 2: When are tolerances for a Work Package agreed?...
Question 3: Which is a purpose of the Project Product Description?...
Question 4: Identify the missing words in the following sentence. A Proj...
Question 5: Which is a responsibility of a Team Manager?...
Question 6: Whose approval is needed to replace a Stage Plan with an Exc...
Question 7: Which is an objective of the Directing a Project process?...
Question 8: Which product records any project outcomes perceived as nega...
Question 9: Which is NOT one of the levels of plan recommended by PRINCE...
Question 10: Which is an objective of the quality review technique?...
Question 11: Identify the missing words in the following sentence, The si...
Question 12: Which task is performed by the Change Authority?...
Question 13: Which is a valid statement about the Project Support role?...
Question 14: Which statement about the Directing a Project process is tru...
Question 15: Which is a purpose of the Controlling a Stage process?...
Question 16: Why is the Initiating a Project process used?...
Question 17: Identify the missing words in the following sentence. At an ...
Question 18: Which is a PRINCE2 time-driven control?...
Question 19: Which is a true statement about PRINCE2 event-driven control...
Question 20: Which PRINCE2 principle is supported by the setting of toler...
Question 21: Which product documents the information needed to demonstrat...
Question 22: Which does the Executive need to ensure is in place before t...
Question 23: Identify the missing word in the following sentence, A purpo...
Question 24: What do customer's quality expectations identify?...
Question 25: Identify the missing word in the following sentence. The ris...
Question 26: Which is a purpose of a Lessons Log?...
Question 27: Why does PRINCE2 recommend three different levels of plans?...
Question 28: Which statement about the Directing a Project process is FAL...
Question 29: Which plan provides the Business Case with costs during the ...
Question 30: What is a purpose of a Benefits Review Plan?...
Question 31: Which characteristic distinguishes a project from regular bu...
Question 32: What product records any time tolerances agreed between the ...
Question 33: How is a Benefits Review Plan used in the Closing a Project ...
Question 34: Which is a purpose of the Business Case theme?...
Question 35: Identify the missing words in the following sentence. The [ ...
Question 36: Which is performed as part of the recommended risk managemen...
Question 37: Where should a Team Manager look for information on the qual...
Question 38: Which is an objective of the Directing a Project process?...
Question 39: Which is a true statement about time-driven controls?...
Question 40: Who carries out audits that are independent of the project?...
Question 41: Which statement is FALSE?
Question 42: Which is a purpose of the Risk theme?...
Question 43: Which is a purpose of the Risk Register?...
Question 44: How should the Team Manager report that tolerances are forec...
Question 45: Which is NOT considered when defining risk tolerance?...
Question 46: Which should be used to document any uncompleted work that n...
Question 47: Which of the following statements about customer's quality e...
Question 48: Which is a purpose of an End Stage Report?...
Question 49: Which of the following is NOT part of quality control?...
Question 50: Identify the missing words in the following sentence. The ro...
Question 51: Which should be funded from a change budget?...
Question 52: Which project characteristic suggests that projects should h...
Question 53: What process is used by the Project Manager to maintain focu...
Question 54: Which is a purpose of the Risk theme?...
Question 55: How many management stages should a PRINCE2 project consist ...
Question 56: What plan is created, and submitted for approval, during the...
Question 57: Identify the missing words in the following sentence. Config...
Question 58: Which is NOT confirmed during the Initiating a Project proce...
Question 59: Identify the missing words in the following sentence. A prob...
Question 60: What do acceptance criteria identify?...
Question 61: Which is a purpose of a Configuration Management Strategy?...
Question 62: Which is one of the three levels of plan in PRINCE2?...
Question 63: Which product describes the roles and responsibilities for a...
Question 64: Which of the following is NOT an event-driven control?...
Question 65: Identify the missing words in the following sentence. The pu...
Question 66: Which is a purpose of a Risk Register?...
Question 67: Identify the missing words in the following sentence. A purp...
Question 68: Which of the following refers to the actions identified to b...
Question 69: Who does the Team Manager report to and take direction from?...
Question 70: Which is part of quality control?...
Question 71: Which task is performed by the Change Authority?...
Question 72: What process ensures focus on the delivery of a stage's prod...
Question 73: Which role is responsible for creating Checkpoint Reports?...
Question 74: Which is a purpose of an Issue Report?...
Question 75: Which is a recommended quality review team role?...
Question 76: What is the definition of a project outcome?...
Question 77: Identify the missing words in the following sentence. When p...
Question 78: During the Initiating a Project process, which product is up...
Question 79: When considering risks, which describes an opportunity in a ...
Question 80: If Work Package tolerance is forecast to be exceeded, to who...
Question 81: Which role is responsible for the management of a risk assig...
Question 82: Which is NOT a PRINCE2 principle?...
Question 83: Which product summarizes progress and is used to decide whet...
Question 84: What theme provides all management levels within the project...
Question 85: When should the Project Board refer to corporate or programm...
Question 86: Who should use the information in a Lessons Report to refine...
Question 87: Which is a typical core activity within configuration manage...
Question 88: Which is a benefit of using PRINCE2?...
Question 89: Which is NOT represented by one of the three primary categor...
Question 90: Which is a true statement about acceptance criteria?...
Question 91: Which may be funded from a risk budget?...
Question 92: Identify the missing word(s) in the following sentence. Duri...
Question 93: Which is NOT obtained from a product's Product Description?...
Question 94: Which is a purpose of a Project Brief?...
Question 95: Which is an objective of the Starting up a Project process?...
Question 96: Which document should record the agreed amount of risk budge...
Question 97: Which of the following are typical core activities within co...
Question 98: Which may be funded from a risk budget?...
Question 99: Which statement about risks is FALSE?...
Question 100: What product should be used to confirm the version number of...
Question 101: Identify the missing words in the following sentence. A prob...
Question 102: Which process provides the Project Board with the informatio...
Question 103: Which is a difference between management and technical stage...
Question 104: Which process is used by a Team Manager to coordinate work o...
Question 105: Which is a type of issue?