Valid PRINCE2-Agile-Practitioner Dumps shared by ExamDiscuss.com for Helping Passing PRINCE2-Agile-Practitioner Exam! ExamDiscuss.com now offer the newest PRINCE2-Agile-Practitioner exam dumps, the ExamDiscuss.com PRINCE2-Agile-Practitioner exam questions have been updated and answers have been corrected get the newest ExamDiscuss.com PRINCE2-Agile-Practitioner dumps with Test Engine here:

Access PRINCE2-Agile-Practitioner Dumps Premium Version
(50 Q&As Dumps, 35%OFF Special Discount Code: freecram)

<< Prev Question Next Question >>

Question 3/22

Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
a marketing campaign to promote the event;
a celebrity to open the event;
a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.
There are 30 vendor stalls selling products related to the event.
The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
It has been agreed that supervised access to the vendor stalls will only be allowed between 16:00 and 20:00 on the day before the event to allow set-up.
Which is the BEST means of communicating these arrangements to all of the vendors?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (22q)
Question 1: Which is a reason for 'blending and weaving' PRINCE2 with ag...
Question 2: Which is a benefit that can be realized by a PRINCE2 organiz...
Question 3: Project scenario - Get fit with football! (Note: The compani...
Question 4: Project scenario - Get fit with football! (Note: The compani...
Question 5: Project scenario - Get fit with football! (Note: The compani...
Question 6: Project scenario - Get fit with football! (Note: The compani...
Question 7: Project scenario - Get fit with football! (Note: The compani...
Question 8: Project scenario - Get fit with football! (Note: The compani...
Question 9: Project scenario - Get fit with football! (Note: The compani...
Question 10: Which describes a characteristic of business as usual (BAU) ...
Question 11: Project scenario - Get fit with football! (Note: The compani...
Question 12: Project scenario - Get fit with football! (Note: The compani...
Question 13: Project scenario - Get fit with football! (Note: The compani...
Question 14: Project scenario - Get fit with football! (Note: The compani...
Question 15: Project scenario - Get fit with football! (Note: The compani...
Question 16: Project scenario - Get fit with football! (Note: The compani...
Question 17: Project scenario - Get fit with football! (Note: The compani...
Question 18: Project scenario - Get fit with football! (Note: The compani...
Question 19: Project scenario - Get fit with football! (Note: The compani...
Question 20: Project scenario - Get fit with football! (Note: The compani...
Question 21: Project scenario - Get fit with football! (Note: The compani...
Question 22: Project scenario - Get fit with football! (Note: The compani...