Question 28/31

Which TWO project board responsibilities are specifically assigned to the senior user?
1) Demonstrating the achievement of benefits.
2) Specifying the needs of those impacted by the outputs.
3) Balancing business, user and supplier demands.
4) Ensuring that the project delivers value for money.

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (31q)
Question 1: Which is an advantage of frequent releases?...
Question 2: Which statement explains the target 'be on time and hit dead...
Question 3: Which statement about the 'directing a project' process is C...
Question 4: Why is Lean Startup included in the 'starting up a project' ...
Question 5: What information is NOT typically displayed on a burn chart?...
Question 6: What is the MOST LIKELY benefit from frequent releases into ...
Question 7: How should team working agreements be created?...
Question 8: Which statement about the 'keep teams stable' target is CORR...
Question 9: What should be decided when configuring PRINCE2 effectively?...
Question 10: Which process can take place during a release review worksho...
Question 11: Which statement describes how the PRINCE2 'starting up a pro...
Question 12: Which statement about timeboxes is CORRECT?...
Question 13: Which statement about the 'protect the level of quality' tar...
Question 14: What is an epic?
Question 15: Which TWO statements describe a purpose of the business case...
Question 16: How does agile address the risk associated with the project ...
Question 17: Which statement defines a PRINCE2 principle?...
Question 18: Which statement BEST describes the PRINCE2 Agile guidance fo...
Question 19: Which statement about the 'initiating a project' process is ...
Question 20: When tailoring PRINCE2, what does PRINCE2 Agile guidance cov...
Question 21: When tailoring the plans theme in an agile environment, what...
Question 22: According to PRINCE2 Agile, which form of communication show...
Question 23: Which statement about an epic is CORRECT?...
Question 24: Which is an advantage of using the PRINCE2 Agile behavior 'c...
Question 25: Which describes the Scrum Master role in Scrum?...
Question 26: Which is a purpose of the plans theme?...
Question 27: Which is a purpose of the quality theme?...
Question 28: Which TWO project board responsibilities are specifically as...
Question 29: During which process should release planning be done for the...
Question 30: Which statement about the waterfall methodology definition i...
Question 31: Which BEST describes the senior user role when tailoring the...