<< Prev Question Next Question >>

Question 242/309

What cost estimating approach uses the work breakdown structure to create a cost estimate?

LEAVE A REPLY

Your email address will not be published. Required fields are marked *

Question List (309q)
Question 1: Your program has a budget at completion of $1,550,000 and is...
Question 2: Molly is the program manager for her organization. She is cr...
Question 3: You are the program manager of the HNG Program. This program...
Question 4: You are the program manager for your organization. Your curr...
Question 5: A project manager in your program has estimated the cost of ...
Question 6: You are the program manager for your organization. You are p...
Question 7: A program has a BAC of $1,750,000 and is expected to last tw...
Question 8: You are the program manager for your organization. Managemen...
Question 9: Rick is a Program Manager for a large construction program. ...
Question 10: Which one of the following is not an output of the direct an...
Question 11: A program has been established and preparation is complete. ...
Question 12: Which of the following is used to build consensus through ro...
Question 13: An IT program manager is concerned that a program is not ach...
Question 14: A program manager prepares the program for review to secure ...
Question 15: Joan is the program manager for her organization. Throughout...
Question 16: As a program manager you must also understand the project ma...
Question 17: A program manager is leading a program to transform an organ...
Question 18: A large infrastructure development program involves three ro...
Question 19: Which of the following documents describes the details for e...
Question 20: All of the following are resources that need to be monitored...
Question 21: After new private equity owners acquire an enterprise, they ...
Question 22: You are the program manager for your organization. Your prog...
Question 23: Part of program management is to identify what motivates you...
Question 24: The program sponsor returns from a board of directors meetin...
Question 25: Molly is the program manager for her organization and she is...
Question 26: Your program has 121 stakeholders that you'll need to commun...
Question 27: An organization supports both programs and projects for vari...
Question 28: You are identifying stakeholders for your program to create ...
Question 29: A software development program will launch iterative version...
Question 30: You are the program manager for your project. You are workin...
Question 31: Which of the following statements is the most accurate when ...
Question 32: Your program has just been chartered during the program init...
Question 33: Throughout a multiyear program, component projects are trans...
Question 34: You are the program manager for your organization and are wo...
Question 35: A program manager notices that one project manager tends to ...
Question 36: During the execution phase of a program, a stakeholder compl...
Question 37: A program has a BAC of $1,750,000 and is expected to last tw...
Question 38: A program manager is working on benefits. The program team c...
Question 39: You are the program manager for your organization. Your curr...
Question 40: A program delivers incremental benefits, but is far from clo...
Question 41: An organization is considering a new program. The business a...
Question 42: You are the program manager for your organization. You are p...
Question 43: You are the program manager for your organization. You're cu...
Question 44: Which of the following documents describes the details for e...
Question 45: You are the program manager for your organization and you're...
Question 46: Which of the following increases when one fast tracks the pr...
Question 47: You are trying to determine if you should buy or build a sol...
Question 48: A new program is being initiated for the HNQ Organization. T...
Question 49: Robert's program is slipping on its schedule and management ...
Question 50: Which of the following can be used to help you or other proj...
Question 51: In a program, management would like to consider the present ...
Question 52: Which of the following information gathering techniques is d...
Question 53: The program manager must define the program and understand t...
Question 54: At what point in the project is the risk of failing to achie...
Question 55: Hal is the program manager for his organization. He would li...
Question 56: Which of the following terms is used for a schedule compress...
Question 57: A program stakeholder is concerned about information they re...
Question 58: You are the program manager for your organization and you're...
Question 59: Eric is the project manager of the NQQ Project and has hired...
Question 60: A program to implement a company's new system is nearing com...
Question 61: Which benefit measurement method considers the value of each...
Question 62: A company CEO issues a mandate to automate a new-client onbo...
Question 63: You are the program manager of the BHG Program. One of the p...
Question 64: A program is near completion and the benefits will be delive...
Question 65: Who prepares the statement of work (SOW) for external projec...
Question 66: When should a program manager approve the closure of a compo...
Question 67: You are the program manager of the YHT Program. You have bee...
Question 68: You have completed a project for a client at his facility. T...
Question 69: When is the lessons learned document updated?...
Question 70: A team member has made a mistake during the installation of ...
Question 71: The number of emerging risks increases in a component projec...
Question 72: The program manager plans to address a negative cost varianc...
Question 73: What does CPI value less than 1.0 indicates?...
Question 74: Status information, including program and component status, ...
Question 75: In your organization there are rules and procedures that the...
Question 76: Harriet is the program manager of a large program that has a...
Question 77: Which of the following serves as a guiding principle for a p...
Question 78: In your organization there are rules and procedures that the...
Question 79: You are the program manager for your company and are monitor...
Question 80: A program manager has been assigned to a program that has re...
Question 81: What should a program manager do when a scope change has bee...
Question 82: After program closure, the lessons learned document becomes ...
Question 83: Which of the following documents is described in the stateme...
Question 84: Which of the following individual should respond to the risk...
Question 85: Which one of the following is the best example of transferen...
Question 86: A company is releasing a new product geared toward a specifi...
Question 87: Which of the following is responsible to sign off on the clo...
Question 88: A program manager is appointed to manage a new program. The ...
Question 89: You are the program manager for the HGQ Program in your orga...
Question 90: Your program has just been chartered during the program init...
Question 91: A program experiences issues during execution. The stakehold...
Question 92: A component project of a program is completed, and will prov...
Question 93: In your organization there are rules and procedures that the...
Question 94: During program execution, a program manager receives feedbac...
Question 95: Which of the following statements are true regarding the Mon...
Question 96: What is the formula to determine earned value (EV) for a pro...
Question 97: Your program has a budget at completion of $1,550,000 and is...
Question 98: A large program consists of several component projects and s...
Question 99: Your program is to construct a new condo building in Chicago...
Question 100: A program sponsor is concerned about the status of high-prio...
Question 101: A country is in the process of strengthening its defense pro...
Question 102: You are the project manager for your organization. Your proj...
Question 103: Don is the project manager of the NQP Project for his organi...
Question 104: You are the program manager of the NQA Program. In this prog...
Question 105: If a risk has a probability of 60 percent and an impact of -...
Question 106: As a program manager you must also understand the project ma...
Question 107: Which of the following statements is the most accurate when ...
Question 108: A new program is being initiated for the HNQ Organization. T...
Question 109: You need to create a document that will define the costs, re...
Question 110: You are the program manager of the NHQ Program. The program ...
Question 111: As a program manager you must also understand the project ma...
Question 112: Which of the following tools and techniques are parts of the...
Question 113: What is the other name for critical delivery dates?...
Question 114: You are the program manager for your organization. Your curr...
Question 115: A new program is comprised of four component projects. The p...
Question 116: How does a portfolio's collection of work differ from that o...
Question 117: In a program's definition phase, a program manager in countr...
Question 118: You are the program manager of the YHT Program. You have bee...
Question 119: In which of the following processes is the program charter c...
Question 120: You are the program manager for your organization and are wo...
Question 121: A program experiences issues during execution. The stakehold...
Question 122: A global enterprise resource planning (ERP) program's scope ...
Question 123: You are the program manager for the HQM Program. Your progra...
Question 124: Paula is program manager for her organization. It has come t...
Question 125: A multiyear program is ready to conclude. It has achieved al...
Question 126: All of the following information is defined in the program s...
Question 127: One of the constituent project managers asks a new program m...
Question 128: A program manager is responsible for constructing a US$50 mi...
Question 129: Stakeholders ask the program manager to assess reasons for t...
Question 130: Your program has been selected and its program charter is no...
Question 131: You are the program manager for your organization and are wo...
Question 132: During the last steering committee meeting, a program manage...
Question 133: After meeting with the program sponsor and stakeholders, the...
Question 134: You are hosting a meeting with all of the vendors that have ...
Question 135: You are the program manager for your organization. Your prog...
Question 136: You are the project manager for the GGG Project and are abou...
Question 137: You are the program manager for your organization and are pl...
Question 138: Ned is the program manager for his organization and he's con...
Question 139: A program manager concurrently implements a software program...
Question 140: Which of the following terms is used for a schedule compress...
Question 141: You work as a program manager for a large construction progr...
Question 142: You are the program manager of the OFE Program. You are work...
Question 143: In which of the following processes is the program charter c...
Question 144: Robert's program is slipping on its schedule and management ...
Question 145: After a company's senior executive management meeting, the C...
Question 146: You are the program manager for your organization. Your prog...
Question 147: Which of the following documents sets the project objectives...
Question 148: In preparation for the development and submission of the pro...
Question 149: You are the program manager for the NHQ Program. Your progra...
Question 150: The chief executive officer (CEO) informs the program manage...
Question 151: You are the program manage of HYH Program for your organizat...
Question 152: Performing quality assurance in a program can result in whic...
Question 153: An infrastructure program has 20 projects. The first half of...
Question 154: Identify the term described in the statement given below? "T...
Question 155: Marty is the project manager of the recently completed NHK P...
Question 156: Who makes Go/No-Go decisions during phase gate reviews?...
Question 157: Small changes that bypass the organization's change control ...
Question 158: You have created a control chart for a repeatable process in...
Question 159: A program manager learns that their company's organizational...
Question 160: You are program manager for the HYH Program. Your program go...
Question 161: All of the following are benefits of a program except for wh...
Question 162: Which of the following tools and techniques are parts of the...
Question 163: You are the program manager for your organization. Managemen...
Question 164: Small changes that bypass the organization's change control ...
Question 165: You are the program manager for your organization and are pl...
Question 166: You are the program manager for a construction program. In t...
Question 167: What schedule analysis simulation tool allows you, the proje...
Question 168: You are the program manager for your organization. As your p...
Question 169: You are the program manager for the JQN Program in your orga...
Question 170: You are the program manager for your organization. Your prog...
Question 171: There are 1,500 doors to be installed in Tom's program. Each...
Question 172: A program manager is identifying and verifying risks as outl...
Question 173: What component of the change management system is responsibl...
Question 174: Hans is the program manager for his organization. His curren...
Question 175: You are the program manager for your organization and you ar...
Question 176: There are five stages of team development. At which stage ar...
Question 177: Which of the following documents sets the project objectives...
Question 178: An organization is considering a new program. The program ha...
Question 179: You are the program manager for your organization. Your curr...
Question 180: You are working with Sam, a project manager on one of the pr...
Question 181: You are the program manager for a large program in your matr...
Question 182: What is the present value of a program that will be worth $3...
Question 183: You are the program manager for your organization. You have ...
Question 184: Program management has several themes that the program manag...
Question 185: You are the project manager for your organization. Your proj...
Question 186: You are the program manager for your organization. Your prog...
Question 187: You are the program manager for the SRQ Program. You have re...
Question 188: As a Program Manager, you decide to take the team on an outi...
Question 189: You are the program manager for your organization. Your prog...
Question 190: You are the program manager of a new program in your organiz...
Question 191: Paul is the program manager for his company. He along with h...
Question 192: Don is the project manager of the NQP Project for his organi...
Question 193: You work as a program manager for a large construction progr...
Question 194: You are the program manager for your organization. Your prog...
Question 195: A new program is being initiated for the HNQ Organization. T...
Question 196: An initiative involves the development of new technology and...
Question 197: You are coaching Tammy, a project manager in your program, o...
Question 198: A new program manager joins a multi-year program that has be...
Question 199: You work as a program manager for a large construction progr...
Question 200: What duration compression technique typically adds risk when...
Question 201: You are the program manager for your organization. You and y...
Question 202: You are the program manager for your organization and you ar...
Question 203: Your program exists within a matrix structure. Your program ...
Question 204: Part of your job as the program manager is to coach the proj...
Question 205: Your program has a budget at completion of $1,550,000 and is...
Question 206: You are the program manager for your organization and your t...
Question 207: You are the program manager for your organization. As your p...
Question 208: You are the program manager for your organization and are ab...
Question 209: Part of program management is to understand how the communic...
Question 210: You are the program manager for your organization and are wo...
Question 211: Your program has a budget at completion of $1,550,000 and is...
Question 212: You are a program manager for a large construction program. ...
Question 213: You are the program manager for your company and are monitor...
Question 214: The program manager defines the program objectives, requirem...
Question 215: An organization supports both programs and projects for vari...
Question 216: Which one of the following is the best definition of program...
Question 217: Robert is the program manager of the NHQ Program. His team h...
Question 218: You are the program manager for the HGQ Program in your orga...
Question 219: What should a program manager do when a scope change has bee...
Question 220: You are the program manager for your organization. Your prog...
Question 221: Which one of the following is not an output of the direct an...
Question 222: A program manager initiates a developmental program. Signifi...
Question 223: You are trying to determine if you should buy or build a sol...
Question 224: You are the program manager for your organization. You're cu...
Question 225: You are the program manager for your organization. You are p...
Question 226: Alice is the project manager of the NHQ Project and is enter...
Question 227: (Exhibit) The above performance report shows the earned valu...
Question 228: A software company's program manager is conducting closing p...
Question 229: You are the program manager for your organization and you ne...
Question 230: An IT program manager is concerned that a program is not ach...
Question 231: Over the life of your program you've received many change re...
Question 232: Mary has just completed a large program for her organization...
Question 233: Gary is program manager for his organization. His current pr...
Question 234: Which of the following risk response planning techniques is ...
Question 235: A risk response in a project in your program has actually ca...
Question 236: You are the program manager of the GHY Program in your organ...
Question 237: Which of the following statements are true regarding program...
Question 238: You are the program manager of the YGH Program. A vendor has...
Question 239: Which of the following statements are true regarding program...
Question 240: You are the program manager for your organization. You're cu...
Question 241: Complete the following phrase about quality management: Qual...
Question 242: What cost estimating approach uses the work breakdown struct...
Question 243: Which of the following statements are true regarding the Mon...
Question 244: You are the program manager of the HNG Program. This program...
Question 245: You are the program manager of the NQA Program. In this prog...
Question 246: You are the program manager for your organization. Managemen...
Question 247: You are the program manager for a new software development p...
Question 248: You are the project manager for your organization. Your proj...
Question 249: Which of the following tools and techniques are parts of the...
Question 250: An organization is considering a new program. The program ha...
Question 251: Which of the following is not a phase of program life cycle?...
Question 252: A regional finance program is impacted by a new currency reg...
Question 253: Joan is the program manager for her organization. Management...
Question 254: A program governance board mandates that phase gate reviews ...
Question 255: A program has a BAC of $1,750,000 and is expected to last tw...
Question 256: You are the program manager for your program and are creatin...
Question 257: You are the program manager for your company and evaluating ...
Question 258: Complete the following phrase about quality management: Qual...
Question 259: You are the program manager for your organization. This prog...
Question 260: Your program will create new software and install new hardwa...
Question 261: What does CPI value less than 1.0 indicates?...
Question 262: You are the program manager for the JQN Program in your orga...
Question 263: After program closure, the lessons learned document becomes ...
Question 264: What would prevent a program manager from completing program...
Question 265: One of the constituent project managers asks a new program m...
Question 266: Which of the following documents provides the mandate to exe...
Question 267: Company A recently signed a contract with a strategic busine...
Question 268: When a change enters your program requirements you must upda...
Question 269: You are the program manager of the NHQ Program. You are work...
Question 270: You are the project manager for the GGG Project and are abou...
Question 271: You are the program manager for your organization. Your prog...
Question 272: You are the program manager for your organization and are re...
Question 273: You are the program manager for your organization and are co...
Question 274: Which of the following directs the improvement efforts to th...
Question 275: During the selection of source process, you assign certain p...
Question 276: Paula is program manager for her organization. It has come t...
Question 277: You are the program manager for your organization. Part of y...
Question 278: What percentage of communication is nonverbal?...
Question 279: During the program execution stage, the component project ma...
Question 280: A program manager is concerned because several change reques...
Question 281: You are a program manager of a program. You are required to ...
Question 282: Your program has 121 stakeholders that you'll need to commun...
Question 283: Which of the following increases when one fast tracks the pr...
Question 284: A program sponsor is concerned about the status of high-prio...
Question 285: Which of the following serves as a guiding principle for a p...
Question 286: What does RACI stand for?
Question 287: What is another term that can be assigned to the pre-program...
Question 288: You are the program manager for your organization. This prog...
Question 289: You are the program manager of the YHT Program. You have bee...
Question 290: A program with six projects has been running for three years...
Question 291: Your program will create new software and install new hardwa...
Question 292: You are the program manager of the NHQ Program for your orga...
Question 293: The customer of a three-year program does not want to receiv...
Question 294: Julie is the program manager of the NHQ Program for her orga...
Question 295: You are the program manager for your organization and are pl...
Question 296: A program in a matrix organization includes subprojects for ...
Question 297: According to Standard for Program Management, Second Edition...
Question 298: Wan is the program manager for his organization. He has been...
Question 299: A program has a budget at completion of $1,250,000 and has a...
Question 300: Terri is the program manager for her organization and she's ...
Question 301: A program manager recognizes that a successful resource bein...
Question 302: Over the life of your program you've received many change re...
Question 303: In your program you must adhere to Six Sigma as part of your...
Question 304: Two project managers in your program, Marcy and Mary, are no...
Question 305: A wild life protection organization opposes your program, wh...
Question 306: The program charter for a new, five-component program has be...
Question 307: Wanda is the program manager for her organization. Her progr...
Question 308: A program includes the development and shipping of 12 millio...
Question 309: Which one of the following is NOT a component of the risk mo...