During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?
Correct Answer: B
The first thing that the project manager should do is to meet with the team to discuss alternatives. This option allows the project manager to identify the root cause of the problem, evaluate the impact of the deliverable on the project scope, quality, cost and time, and explore possible solutions with the team's input. The project manager can then communicate the issue and the proposed solutions to the project sponsor and other stakeholders for resolution.